Worked example
Example: Shallow lagoon 1.5 m, 0 to 6 mg/L. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Saturation dissolved oxygen | 8.2600 mg/L |
| Initial dissolved oxygen | 0 mg/L |
| Target dissolved oxygen | 6.0000 mg/L |
| Liquid film coefficient | 0.020000 m/h |
| Surface area | 20,000 m² |
| Depth | 1.5000 m |
Applying the formula below gives:
| Result | Value |
|---|---|
| Interfacial area per volume | 0.66667 1/m |
| Overall coefficient | 0.013333 1/h |
| Time required | 4.0502 d |
Open this example in the calculator and change any input.
Formula
\(\frac{C_s - C_t}{C_s - C_o} = e^{-K_Lat}, \quad a = \frac{A}{V} = \frac{1}{h}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(C_s\) | Saturation dissolved oxygen | kg/m³ |
| \(C_o\) | Initial dissolved oxygen | kg/m³ |
| \(C_t\) | Target dissolved oxygen | kg/m³ |
| \(K_L\) | Liquid film coefficient | m/s |
| \(A\) | Surface area | m² |
| \(h\) | Depth | m |
| \(a\) | Interfacial area per volume | 1/m |
| \(K_La\) | Overall coefficient | 1/s |
| \(t\) | Time required | s |
Method and standards
First-order gas absorption.
Where it is used
- Storage basins and lagoons for reuse water.
- Estimating natural reaeration.
Common mistakes
- Using the volume instead of the area in a.
- Taking K_L for a stagnant surface.
Assumptions and limits
- Uniform mixing; constant temperature.
Questions and answers
Is the surface area the same as A in K_La?
Here the specific area a is the surface area divided by the volume, which for a basin of uniform depth is 1/h.
What K_L should I use?
For gently mixed open basins about 0.01-0.05 m/h; Designers use 0.03 m/h for oxygen.
What do the defaults represent?
An illustrative case: Shallow lagoon 1.5 m, 0 to 6 mg/L. Replace the inputs with your own data.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Metcalf and Eddy (Tchobanoglous, Stensel, Tsuchihashi and Burton), Wastewater Engineering: Treatment and Resource Recovery, 5th ed. (McGraw-Hill, 2014), sec. 5-10, eq. 5-63 and Example 5-12