Worked example
Example: Illustrative: f0 75, fc 10 mm/h, k 4/h, rain 30 mm/h, 1 h. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Initial infiltration capacity | 75.000 mm/h |
| Final (steady) infiltration capacity | 10.000 mm/h |
| Decay constant | 4.0000 1/h |
| Time since the start of rain | 1.0000 h |
| Rainfall intensity (0 to skip runoff) | 30.000 mm/h |
Applying the formula below gives:
| Result | Value |
|---|---|
| Infiltration capacity at t | 11.191 mm/h |
| Cumulative infiltration to t | 25.952 mm |
| Rainfall excess to t (rain always at or above capacity after ponding) | 9.4044 mm |
| Time for capacity to fall to the rain intensity | 0.29466 h |
Open this example in the calculator and change any input.
Formula
\(f(t) = f_c + (f_0 - f_c)e^{-kt}, \quad F(t) = f_c t + \frac{f_0 - f_c}{k}\left(1 - e^{-kt}\right)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(f_0\) | Initial infiltration capacity | m/s |
| \(f_c\) | Final (steady) infiltration capacity | m/s |
| \(k\) | Decay constant | 1/s |
| \(t\) | Time since the start of rain | s |
| \(i\) | Rainfall intensity (0 to skip runoff) | m/s |
| \(f(t)\) | Infiltration capacity at t | m/s |
| \(F(t)\) | Cumulative infiltration to t | m |
| \(R\) | Rainfall excess to t (rain always at or above capacity after ponding) | m |
| \(t_c\) | Time for capacity to fall to the rain intensity | s |
Method and standards
Empirical exponential infiltration decay.
Where it is used
- Urban drainage and runoff modelling.
- Irrigation scheduling and soil assessment.
Common mistakes
- Using hourly k with times in minutes.
- Applying the capacity curve when the rain is lighter than the capacity.
Assumptions and limits
- Water ponded at the surface; homogeneous soil.
References
- Horton's infiltration equation
Questions and answers
Where do f₀, f_c and k come from?
From infiltrometer tests fitted to the curve; typical sandy loam values are f₀ ≈ 70–250 mm/h, f_c ≈ 10–25 mm/h and k ≈ 2–5 per hour.
Is Horton better than the SCS curve number?
Horton describes the rate over time for a site with test data; the curve number is for event runoff volumes over a catchment.
What do the defaults represent?
An illustrative soil with f₀ = 75 mm/h, f_c = 10 mm/h and k = 4 per hour under 30 mm/h of rain, after one hour.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Chow, Maidment and Mays, Applied Hydrology (McGraw-Hill, 1988), sec. 4.3