Worked example
Example: 500 t/d from 4 % to 1 %. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Pulp production (oven-dry) | 500.00 t/d |
| Present consistency | 4.0000 % |
| Target consistency | 1.0000 % |
| Stock density | 1,000.0 kg/m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Stock flow at C₁ | 520.83 t/h |
| Volume flow at C₁ | 144.68 L/s |
| Stock flow at C₂ | 2,083.3 t/h |
| Water to add (+) or remove (−) | 1,562.5 t/h |
| Volume flow at C₂ | 578.70 L/s |
Open this example in the calculator and change any input.
Formula
\(\dot m = \frac{\dot m_{OD}}{C}, \quad \Delta\dot m_w = \dot m_{OD}\left(\frac{1}{C_2} - \frac{1}{C_1}\right)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(\dot m_{OD}\) | Pulp production (oven-dry) | kg/s |
| \(C_1\) | Present consistency | - |
| \(C_2\) | Target consistency | - |
| \(\rho\) | Stock density | kg/m³ |
| \(\dot m_1\) | Stock flow at C₁ | kg/s |
| \(\dot V_1\) | Volume flow at C₁ | m³/s |
| \(\dot m_2\) | Stock flow at C₂ | kg/s |
| \(\Delta\dot m_w\) | Water to add (+) or remove (−) | kg/s |
| \(\dot V_2\) | Volume flow at C₂ | m³/s |
Method and standards
Fibre balance.
Where it is used
- Stock preparation and pump sizing.
- Dilution control.
Common mistakes
- Using % in place of fractions.
- Forgetting fillers in consistency.
Assumptions and limits
- Stock density close to water.
References
- Smook
- Handbook for Pulp & Paper Technologists
- 3rd ed. (Angus Wilde, 2002)
- ch. 9 (consistency: OD fibre as a share of stock mass)
Questions and answers
What is consistency?
Oven-dry fibre as a percentage of the total stock mass.
How much water does dilution take?
From 4 % to 1 % multiplies the stock flow by four: three parts of water per part of stock.
Why do flows rise so fast at low consistency?
Flow is inversely proportional to consistency: the headbox at 0.5 % carries 200 t of water per t of fibre.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.