Worked example
Example: 30 days, 2.4 days down. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Calendar time in the period | 720.00 h |
| Downtime (breaks, shuts, grade changes) | 57.600 h |
| Reel production while running | 49.000 t/h |
| Broke as a share of reel output | 6.0000 % |
| Speed as a share of the design speed | 97.000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Time efficiency | 92.000 % |
| Material efficiency | 94.000 % |
| Overall efficiency (time × speed × material) | 83.886 % |
| Saleable production in the period | 30,510 t |
| Production lost to downtime | 2,822.4 t |
Open this example in the calculator and change any input.
Formula
\(\eta_t = \frac{T - T_d}{T}, \quad \eta_m = 1 - B, \quad \eta_o = \eta_t\,\eta_m\,P_s\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(T\) | Calendar time in the period | s |
| \(T_d\) | Downtime (breaks, shuts, grade changes) | s |
| \(P_r\) | Reel production while running | kg/s |
| \(B\) | Broke as a share of reel output | - |
| \(P_s\) | Speed as a share of the design speed | - |
| \(\eta_t\) | Time efficiency | - |
| \(\eta_m\) | Material efficiency | - |
| \(\eta_o\) | Overall efficiency (time × speed × material) | - |
| \(M\) | Saleable production in the period | kg |
| \(M_d\) | Production lost to downtime | kg |
Method and standards
Efficiency definitions.
Where it is used
- Monthly KPI reports.
- Loss trees.
Common mistakes
- Counting grade changes as running time.
- Ignoring speed losses.
Assumptions and limits
- Constant running rate.
- With the speed above design speed (share over 100 %) the overall efficiency can exceed 100 %; the page flags it.
References
- Smook
- Handbook for Pulp & Paper Technologists
- 3rd ed. (Angus Wilde, 2002)
- ch. 21 (paper machine efficiency and broke)
Questions and answers
What is good time efficiency?
92–96 % for well-run machines.
Why include speed?
Running slower than design is a hidden loss that time efficiency misses.
Is broke lost?
It is re-pulped, but its drying energy and machine time are lost.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.