Cush-Cush Screen Area and DSM Screen Width

Area of a cush-cush (fine bagasse) screen per t cane/h and its share by mill (Hugot ch. 22), and the width of a DSM curved screen for the juice flow.

Sugar mill and cogeneration

Inputs

Examples: 250 TCH, five mills, 1 mm DSM150 TCH, four mills, 0.7 mm

Results

Hugot: 0.07 m² per t cane/h for 12–14 rollers, 0.08 for 15–17 and 0.09 for 18–20; shares 3 : 2 : 1 : 1 … from the first mill.

Cush-cush screen area10.500m²
Area for the first mill4.5000m²
Area for the second mill3.0000m²
Area for each following mill1.5000m²
DSM screen width2.6667m

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: 250 TCH, five mills, 1 mm DSM. The inputs, in the units selected above:

InputValue
Crushing rate250.00 t/h
Number of 3-roller mills (crusher not counted)5.0000 -
Juice flow to the DSM screen260.00 m³/h
DSM bar spacing1 mm (7 500 L/h per dm)

Applying the formula below gives:

ResultValue
Cush-cush screen area20.000 m²
Area for the first mill7.5000 m²
Area for the second mill5.0000 m²
Area for each following mill2.5000 m²
DSM screen width3.4667 m

Open this example in the calculator and change any input.

Formula

\(S = A(0.03 + 0.01N_m), \quad S_1 : S_2 : S_n = 3 : 2 : 1, \quad W = \frac{\dot V_j}{q_{dm}}, \quad q_{dm} = 7.5\ \mathrm{m^3/h\ per\ dm}\ (1\ \mathrm{mm}),\ 6.0\ (0.7\ \mathrm{mm})\)

Variables

Symbol Meaning SI unit
\(A\) Crushing rate kg/s
\(N_m\) Number of 3-roller mills (crusher not counted) -
\(\dot V_j\) Juice flow to the DSM screen m³/s
\(\text{spacing}\) DSM bar spacing -
\(S\) Cush-cush screen area m²
\(S_1\) Area for the first mill m²
\(S_2\) Area for the second mill m²
\(S_n\) Area for each following mill m²
\(W\) DSM screen width m
\(q_{dm}\) DSM capacity per dm of width, by bar spacing m³/s per m

Method and standards

Hugot's area and capacity rules.

Where it is used

  • Sizing juice screens.
  • Checking screens after a crush increase.

Common mistakes

  • Counting the crusher as a mill.
  • Using mass flow in t/h as m³/h without density.

Assumptions and limits

  • Hugot's rules for normal preparation; fine preparation needs more area.
  • The line 0.03 + 0.01 N_m reproduces Hugot's figures for four to six mills (12–20 rollers); outside that a note says the area is extrapolated.
  • With two mills there is no following mill, so S_n is not shown.

References

  • Hugot
  • Handbook of Cane Sugar Engineering
  • 3rd ed. (Elsevier, 1986)
  • ch. 22
  • screen area and the D.S.M. screen
  • pp. 354–356

Questions and answers

Why does the first mill get the largest share?

It sends the most juice and the most fine bagasse.

DSM spacing?

1 mm as a first screen, 0.7 mm as a second screen; 0.35 mm for clear juice.

Are cush-cush screens still used?

Many new mills return juice with chokeless pumps instead; the DSM or vibrating screen then cleans mixed juice.

Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.