Boiler House Water Balance and Unaccounted Loss

Make-up water that should be needed from steam, condensate return and blowdown, and the unaccounted water loss compared with the metered make-up.

Thermal power plantProcess steam and utilitiesSugar mill and cogenerationChemical and fertiliserBoilerWater treatment plant

Inputs

Examples: Day: make-up 95 t, steam 200 t, condensate 120 t, blowdown 5 %Month: 3600 t, 6000 t, 2700 t, 4 %Poor return: 190 t, 200 t, 20 t, 3 %

Results

Unaccounted water loss60.000t
Unaccounted loss, share of make-up1.6667%
Make-up that should be needed3,540.0t
Condensate return, share of steam45.000%

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Day: make-up 95 t, steam 200 t, condensate 120 t, blowdown 5 %. The inputs, in the units selected above:

InputValue
Make-up water metered in the period95.000 t
Steam generated200.00 t
Condensate returned120.00 t
Blowdown, share of steam (not of feedwater)5.0000 %

Applying the formula below gives:

ResultValue
Unaccounted water loss5.0000 t
Unaccounted loss, share of make-up5.2632 %
Make-up that should be needed90.000 t
Condensate return, share of steam60.000 %

Open this example in the calculator and change any input.

Formula

\(M_e = S - C + b\,S \qquad L = M - M_e \qquad l = \frac{L}{M} \qquad r = \frac{C}{S}\)

Variables

Symbol Meaning SI unit
\(M\) metered make-up water kg
\(S\) steam generated kg
\(C\) condensate returned kg
\(b\) blowdown, share of steam (not of feedwater) –
\(L\) unaccounted water loss kg
\(l\) loss, share of make-up –
\(M_e\) make-up that should be needed kg
\(r\) condensate return, share of steam –

Method and standards

Mass balance of the steam–condensate–feedwater loop over a period.

Where it is used

  • Water audits of boiler houses.
  • Finding leaks and lost condensate.
  • Checking make-up and condensate meters.

Common mistakes

  • Counting blowdown twice (it is already in the make-up need).
  • Using design condensate return instead of measured.
  • Ignoring deaerator vent and soot-blowing steam.

Assumptions and limits

  • Totals for the same period; no change in tank levels.
  • Blowdown is a share of steam here; some sibling calculators use a share of feedwater (b_fw = b_s/(1 + b_s)).
  • Every other use of water (deaerator vent, soot blowing, spray from outside the loop) shows up as unaccounted loss.

References

  • Water mass balance of the boiler house

Questions and answers

How much make-up water should a boiler need?

Steam not returned plus blowdown. 200 t of steam with 120 t of condensate back and 5 % blowdown needs 90 t of make-up; if the meter shows 95 t, 5 t (5.3 %) is lost somewhere.

Where does unaccounted water go?

Leaking valves and traps, overflowing tanks, vents, soot blowing, sampling and meter error.

Why does it matter?

Every tonne of make-up costs water, treatment chemicals and the fuel to heat it; returned condensate is already hot and pure.

Method and article reviewed by FireCAD engineering on 11 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.