Worked example
Example: 40 t hold-up, 2 t/h blowdown. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Boiler water hold-up | 40.000 t |
| Blowdown flow (raised during recovery) | 2,000.0 kg/h |
| Concentration after the upset | 800.00 - |
| Normal steady level at this blowdown | 150.00 - |
| Target level | 300.00 - |
| Time for a check value | 6.0000 h |
Applying the formula below gives:
| Result | Value |
|---|---|
| Time constant M/ṁ_b | 20.000 h |
| Concentration at the check time | 631.53 |
| Time to reach the target | 29.327 h |
Open this example in the calculator and change any input.
Formula
\(\tau = \frac{M}{\dot m_b}, \quad c(t) = c_{ss} + (c_0 - c_{ss})e^{-t/\tau}, \quad t_t = \tau\ln\frac{c_0 - c_{ss}}{c_t - c_{ss}}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(M\) | Boiler water hold-up | kg |
| \(\dot m_b\) | Blowdown flow (raised during recovery) | kg/s |
| \(c_0\) | Concentration after the upset | - |
| \(c_{ss}\) | Normal steady level at this blowdown | - |
| \(c_t\) | Target level | - |
| \(t\) | Time for a check value | s |
| \(\tau\) | Time constant M/ṁ_b | s |
| \(c(t)\) | Concentration at the check time | - |
| \(t_t\) | Time to reach the target | s |
Method and standards
First-order mixing.
Where it is used
- Sugar ingress and condenser leak recovery.
Common mistakes
- Using normal blowdown for the recovery period.
Assumptions and limits
- Fully mixed boiler water.
- The steady level must be the level that the raised blowdown rate gives (it is lower than at normal blowdown); it is your input and is not checked against the flow.
- When the target is not between the upset and steady levels, the time to it is not shown and a note says why.
References
- Completely mixed tank with blowdown: c(t) = c_ss + (c₀ − c_ss) e^{−t ṁ_b/M}
Questions and answers
Why exponential?
Each kilogram blown down removes water at the current concentration, so the excess falls by a constant share per hour.
Speed it up?
Raise blowdown: the time constant is hold-up divided by blowdown flow.
Is the contaminant still coming in?
Then the steady level rises; stop the source first.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.