Worked example
Example: Illustrative k 0.95 to 0.98, 120 cps. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Multiplication factor in state 1 | 0.95000 - |
| Multiplication factor in state 2 | 0.98000 - |
| Count rate in state 1 (counts per second) | 120.00 Hz |
Applying the formula below gives:
| Result | Value |
|---|---|
| Subcritical multiplication 1/(1 − k₁) | 20.000 |
| Subcritical multiplication 1/(1 − k₂) | 50.000 |
| Expected count rate in state 2 | 300.00 1/s |
| Inverse multiplication ratio (approaches 0 at criticality) | 0.40000 |
| Reactivity in state 1 (pcm) | -5,263.2 |
| Reactivity in state 2 (pcm) | -2,040.8 |
Open this example in the calculator and change any input.
Formula
\(M = \frac{1}{1 - k}, \quad \frac{CR_2}{CR_1} = \frac{1 - k_1}{1 - k_2}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(k_1\) | Multiplication factor in state 1 | - |
| \(k_2\) | Multiplication factor in state 2 | - |
| \(CR_1\) | Count rate in state 1 (counts per second) | 1/s |
| \(M_1\) | Subcritical multiplication 1/(1 − k₁) | - |
| \(M_2\) | Subcritical multiplication 1/(1 − k₂) | - |
| \(CR_2\) | Expected count rate in state 2 | 1/s |
| \(CR_1/CR_2\) | Inverse multiplication ratio (approaches 0 at criticality) | - |
| \(\rho_1\) | Reactivity in state 1 (pcm) | - |
| \(\rho_2\) | Reactivity in state 2 (pcm) | - |
Method and standards
Subcritical multiplication.
Where it is used
- Reactor start-up and refuelling operations.
- Critical experiments and training.
Common mistakes
- Expecting a finite count rate at criticality from the source alone.
- Taking large steps when the 1/M plot is near zero.
Assumptions and limits
- Point model; fixed source and detector efficiency.
References
- Subcritical multiplication of a neutron source
Questions and answers
Why does the count rate rise near criticality?
Each source neutron starts a chain of 1/(1 − k) neutrons on average; at k = 0.99 that is 100, so count rates climb steeply.
How is the 1/M plot used?
Operators plot the inverse count rate ratio after each step of rod withdrawal or fuel loading and extrapolate it to zero to predict where criticality will occur, keeping steps small as it approaches.
What do the defaults represent?
An illustrative core at k = 0.95 counting 120 per second, then moved to k = 0.98.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Lamarsh and Baratta, Introduction to Nuclear Engineering, 3rd ed. (Prentice Hall, 2001), ch. 7