Worked example
Example: 450 a day. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Available working time per day | 450.00 min |
| Demand per day | 450.00 - |
| Total work content per unit | 4.2000 min |
| Workstations actually used | 5.0000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Takt time | 60.000 s |
| Minimum workstations (rounded up) | 5.0000 |
| Balance efficiency T_w/(n T_t) | 84.000 % |
Open this example in the calculator and change any input.
Formula
\(T_t = \frac{t_a}{D}, \quad n_{min} = \left\lceil\frac{T_w}{T_t}\right\rceil, \quad \eta_b = \frac{T_w}{n T_t}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(t_a\) | Available working time per day | s |
| \(D\) | Demand per day | - |
| \(T_w\) | Total work content per unit | s |
| \(n\) | Workstations actually used | - |
| \(T_t\) | Takt time | s |
| \(n_{min}\) | Minimum workstations (rounded up) | - |
| \(\eta_b\) | Balance efficiency T_w/(n T_t) | - |
Method and standards
Lean definitions.
Where it is used
- Assembly line design.
- Workshop planning.
Common mistakes
- Using total shift time including breaks.
- Ignoring OEE losses.
Assumptions and limits
With fewer stations than n_min the line cannot meet takt; the balance efficiency then exceeds 100 % and the page warns.
Steady demand.
References
- Takt = available time/demand; n_min = ⌈T_w/T_t⌉; balance efficiency T_w/(n T_t) (lean manufacturing)
Questions and answers
7.5 h for 450 units with 4.2 min of work?
Takt 60 s; at least 5 stations; with 5 stations efficiency 84 %.
Takt vs cycle time?
Takt is demand's pace; each station's cycle time must not exceed it.
Losses?
Plan to OEE: effective takt is shorter.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.