Worked example
Example: Three stages. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Good parts needed | 1,000.0 - |
| Scrap at stage 1 | 3.0000 % |
| Scrap at stage 2 | 5.0000 % |
| Scrap at stage 3 | 2.0000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Overall yield | 90.307 % |
| Starts needed (rounded up) | 1,108.0 |
| Starts minus good parts needed (scrap plus rounding surplus) | 108.00 |
Open this example in the calculator and change any input.
Formula
\(Y = \prod_i (1 - s_i), \quad N_0 = \left\lceil\frac{Q}{Y}\right\rceil, \quad N_s = N_0 - Q\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(Q\) | Good parts needed | - |
| \(s_1\) | Scrap at stage 1 | - |
| \(s_2\) | Scrap at stage 2 | - |
| \(s_3\) | Scrap at stage 3 | - |
| \(Y\) | Overall yield | - |
| \(N_0\) | Starts needed (rounded up) | - |
| \(N_s\) | Starts minus good parts needed (scrap plus rounding surplus) | - |
Method and standards
Chained yields.
Where it is used
- Production planning and costing.
- Quality improvement cases.
Common mistakes
- Adding scrap rates.
- Ignoring rework loops.
Assumptions and limits
- Independent stages; scrap rates are expected averages.
- N_s = N_0 − Q includes the surplus from rounding the starts up (good parts beyond Q), so it can exceed the expected scrap by up to one part per stage; stage-by-stage whole-part scrap may differ.
References
- Rolled throughput yield Y = Π(1 − s_i)
Questions and answers
1000 good parts through 3 %, 5 % and 2 % scrap?
Yield 90.3 %: start 1108.
Why multiply?
Each stage only sees what survived the one before.
Rework?
Parts reworked and passed are not scrap; treat them separately.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.