Worked example
Example: 2000 m3/d at 20 LMH, 35 m2 modules. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Average flow | 2,000.0 m³/d |
| Peak flow factor | 1.5000 - |
| Design net flux at average flow (L/(m²·h)) | 20.000 - |
| Maximum sustainable peak flux (L/(m²·h)) | 35.000 - |
| Time lost to relaxation and backwash | 10.000 % |
| Membrane area per module | 35.000 m² |
Applying the formula below gives:
| Result | Value |
|---|---|
| Membrane area | 4,200.0 m² |
| Modules (rounded up) | 120.00 |
| Gross flux while filtering (L/(m²·h)) | 22.222 |
| Net flux at peak flow (L/(m²·h)) | 29.762 |
Open this example in the calculator and change any input.
Formula
\(A_0 = \frac{Q}{J}, \quad n = \left\lceil\frac{A_0}{A_m}\right\rceil, \quad A = n A_m, \quad J_g = \frac{J}{1 - f_{off}}, \quad J_{peak} = \frac{PF\cdot Q}{nA_m}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(Q\) | Average flow | m³/s |
| \(PF\) | Peak flow factor | - |
| \(J\) | Design net flux at average flow (L/(m²·h)) | - |
| \(J_{p,max}\) | Maximum sustainable peak flux (L/(m²·h)) | - |
| \(f_{off}\) | Time lost to relaxation and backwash | - |
| \(A_m\) | Membrane area per module | m² |
| \(A\) | Membrane area | m² |
| \(n\) | Modules (rounded up) | - |
| \(J_g\) | Gross flux while filtering (L/(m²·h)) | - |
| \(J_{peak}\) | Net flux at peak flow (L/(m²·h)) | - |
Method and standards
Flux definitions.
Where it is used
- Effluent reuse plants.
- Distillery and food MBRs.
Common mistakes
- Designing at peak flux for average flow.
- Forgetting cleaning downtime.
Assumptions and limits
- Net flux design: the area is sized on the net flux J; the downtime share f_off only raises the gross flux while filtering. A is the installed area n A_m (slightly above Q/J).
References
- Metcalf & Eddy
- Wastewater Engineering: Treatment and Resource Recovery
- 5th ed. (McGraw-Hill, 2014)
- ch. 8 (membrane bioreactors: flux and membrane area)
Questions and answers
What is LMH?
Litres per square metre of membrane per hour: the flux.
Why gross and net flux?
Membranes stop for relaxation or backwash; to deliver the net flow they must filter faster while running.
What do the defaults give?
2,000 m³/d at 20 L/(m²·h): 4,200 m² installed, 120 modules of 35 m².
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.