Worked example
Example: 200 µm sand 10 %, 1 m PBT. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Zwietering geometry constant | 6.5000 - |
| Liquid kinematic viscosity | 1.0000 cSt |
| Particle size | 200.00 µm |
| Solid density | 2,650.0 kg/m³ |
| Liquid density | 1,000.0 kg/m³ |
| Solids loading (mass solids per 100 mass liquid) | 10.000 - |
| Impeller diameter | 1.0000 m |
Applying the formula below gives:
| Result | Value |
|---|---|
| Just-suspended speed | 84.202 rpm |
| Tip speed | 4.4088 m/s |
Open this example in the calculator and change any input.
Formula
\(N_{js} = S\,\nu^{0.1}\left(\frac{g\Delta\rho}{\rho_L}\right)^{0.45}X^{0.13}d_p^{0.2}D^{-0.85}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(S\) | Zwietering geometry constant | - |
| \(\nu\) | Liquid kinematic viscosity | m²/s |
| \(d_p\) | Particle size | m |
| \(\rho_s\) | Solid density | kg/m³ |
| \(\rho_L\) | Liquid density | kg/m³ |
| \(X\) | Solids loading (mass solids per 100 mass liquid) | - |
| \(D\) | Impeller diameter | m |
| \(N_{js}\) | Just-suspended speed | 1/s |
| \(\pi DN_{js}\) | Tip speed | m/s |
Method and standards
Zwietering correlation (SI).
Where it is used
- Slurry tanks, crystallisers and leach tanks.
- Agitator selection.
Common mistakes
- Using an S for another impeller.
- X as a fraction rather than per 100 parts.
Assumptions and limits
- Standard baffled tanks.
- X is mass of solids per 100 mass of liquid, not wt % of slurry (10 wt % slurry is X = 11.1).
References
- Zwietering (1958)
- Chem. Eng. Sci. 8: 244; Perry's Chemical Engineers' Handbook
- 9th ed. (McGraw-Hill, 2019)
- sec. 18 (solids suspension)
Questions and answers
Why just-suspended?
Above N_js no particle rests on the base for more than a moment; most dissolution and reaction duties need about this speed, not full uniformity.
How does speed scale with tank size?
At constant geometry N_js ∝ D^−0.85, so power per volume falls somewhat on scale-up.
What do the defaults represent?
Sand-like 200 µm solids at 10 % in water with a 1 m pitched-blade turbine.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.