Worked example
Example: Light oil 25 t/h, 820 kg/m3, 2 mPa s, carbon steel. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Mass flow | 6.9444 kg/s |
| Fluid density | 820.00 kg/m³ |
| Fluid viscosity (for the flow check) | 2.0000 mPa·s |
| Method | Carbon steel cost equation |
Applying the formula below gives:
| Result | Value |
|---|---|
| Optimum inside diameter | 68.364 mm |
| Volume flow | 30.488 m³/h |
| Velocity at the optimum diameter | 2.3072 m/s |
| Reynolds number | 64,669 |
Open this example in the calculator and change any input.
Formula
\(d_{opt} = 293\,G^{0.53}\rho^{-0.37}\ \text{mm (carbon steel)}, \quad d_{opt} = 260\,G^{0.52}\rho^{-0.37}\ \text{mm (stainless)}\)
\(D_{opt} = 0.363\,Q^{0.45}\rho^{0.13}\ \text{m (alternative form, } Q\text{ in m³/s)}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(G\) | Mass flow | kg/s |
| \(\rho\) | Fluid density | kg/m³ |
| \(\mu\) | Fluid viscosity (for the flow check) | Pa·s |
| \(\text{method}\) | Method | - |
| \(d_{opt}\) | Optimum inside diameter | m |
| \(Q\) | Volume flow | m³/s |
| \(u\) | Velocity at the optimum diameter | m/s |
| \(Re\) | Reynolds number | - |
Method and standards
Empirical optimum-diameter equations balancing pipe cost against pumping cost.
Where it is used
- First line sizing on process flow diagrams.
- Checking existing lines for gross over- or undersizing.
Common mistakes
- Using them for steam or slurry lines.
- Taking the result without checking pressure drop and NPSH.
Assumptions and limits
- Turbulent flow; typical cost ratios built into the constants.
Questions and answers
Why does density appear with a negative exponent?
Lighter fluids need more volume per kilogram, so the cost-optimal diameter for the same mass flow is larger.
Why do the methods differ?
They assume different installed pipe costs and power prices; the low installation factor gives larger diameters.
What do the defaults represent?
An illustrative case: Light oil 25 t/h, 820 kg/m3, 2 mPa s, carbon steel. Replace the inputs with your own data.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Sinnott, Coulson and Richardson's Chemical Engineering Vol. 6: Chemical Engineering Design, 4th ed. (Elsevier, 2005), sec. 5.6, eqs. 5.14 and 5.15, Examples 5.6 and 5.7; Peters and Timmerhaus, Plant Design and Economics for Chemical Engineers, 4th ed. (1991)