Massecuite Quantity and Pan Strikes for a Sugar Output

Massecuite to boil for a sugar output from its crystal content, its volume from the massecuite density, and pan strikes per day for a pan capacity.

Sugar mill and cogeneration

Inputs

Examples: 25 t/h sugar, 50 % crystalC massecuite

Results

Massecuite13.333t/h
Massecuite volume8.7719m³/h
Strikes per day4.6784

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: 25 t/h sugar, 50 % crystal. The inputs, in the units selected above:

InputValue
Sugar from this massecuite25.000 t/h
Crystal % massecuite50.000 %
Massecuite density1,500.0 kg/m³
Pan capacity (strike volume)60.000 m³

Applying the formula below gives:

ResultValue
Massecuite50.000 t/h
Massecuite volume33.333 m³/h
Strikes per day13.333

Open this example in the calculator and change any input.

Formula

\(\dot m_m = \frac{\dot m_S}{c_m}, \quad \dot V_m = \frac{\dot m_m}{\rho_m}, \quad N = \frac{86400\,\dot V_m}{V_p}\)

Variables

Symbol Meaning SI unit
\(\dot m_S\) Sugar from this massecuite kg/s
\(c_m\) Crystal % massecuite -
\(\rho_m\) Massecuite density kg/m³
\(V_p\) Pan capacity (strike volume) m³
\(\dot m_m\) Massecuite kg/s
\(\dot V_m\) Massecuite volume m³/s
\(N\) Strikes per day -

Method and standards

Mass balance.

Where it is used

  • Pan station capacity.
  • Boiling scheme studies.

Common mistakes

  • Crystal % solids used as % massecuite.

Assumptions and limits

  • Steady output. The sugar is taken as dry crystal; crystal dissolved by washing in the centrifugals is not counted, so slightly more massecuite is needed in practice.
  • Strikes per day are volume per day over strike volume; pan cycle time (boiling, dropping, steaming out) decides how many pans are needed.

References

  • Crystal balance ṁ_m = ṁ_S/c_m; volume by density

Questions and answers

Why does crystal content matter so much?

Massecuite to boil and centrifuge varies inversely with it.

Massecuite density?

About 1.45–1.55 t/m³ for A to C massecuites.

Strikes per day?

Volume per day over strike volume; add boiling and dropping time for pan count.

Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.