Worked example
Example: 800 m falling 12 m. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Longest flow path | 800.00 m |
| Fall along the flow path | 12.000 m |
| Surface adjustment factor | 1.0000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Average slope ΔH/L | 1.5000 % |
| Time of concentration | 16.865 min |
Open this example in the calculator and change any input.
Formula
\(t_c = 0.0078\, k\, L_{ft}^{0.77}\, S^{-0.385} \ \text{min}, \quad S = \frac{\Delta H}{L}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(L\) | Longest flow path | m |
| \(\Delta H\) | Fall along the flow path | m |
| \(k\) | Surface adjustment factor | - |
| \(S\) | Average slope ΔH/L | - |
| \(t_c\) | Time of concentration | s |
Method and standards
Empirical.
Where it is used
- Plant drainage and storm water design.
- Ash pond and coal yard runoff.
Common mistakes
- L in metres in the feet formula.
- Using it for large catchments.
Assumptions and limits
- Small catchments.
References
- Kirpich
- Z. P. (1940)
- Time of concentration of small agricultural watersheds
- Civil Engineering 10(6): t_c = 0.0078 L^0.77 S^−0.385 (minutes, L in feet)
Questions and answers
800 m flow path falling 12 m?
Slope 1.5 %: t_c about 16.9 minutes.
Why does tc matter?
The rational method uses the rainfall intensity for a storm lasting tc.
Metric form?
t_c = 0.0195 L0.77 S−0.385 with L in metres; it is the same formula.