Worked example
Example: Illustrative magnesium anode column in 20 ohm m soil. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Soil or water resistivity | 2.0000e+07 Ω·mm²/m |
| Anode (or backfill column) length | 1.5000 m |
| Anode (or backfill column) diameter | 200.00 mm |
| Driving voltage (anode to protected structure) | 0.70000 V |
| Total protection current required | 0.60000 A |
Applying the formula below gives:
| Result | Value |
|---|---|
| Anode resistance to earth | 6.5664 Ω |
| Current output per anode | 0.10660 A |
| Anodes needed (rounded up) | 6.0000 |
Open this example in the calculator and change any input.
Formula
\(R_a = \frac{\rho}{2\pi L}\left[\ln\frac{8L}{d} - 1\right], \quad I_a = \frac{\Delta V}{R_a}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(\rho\) | Soil or water resistivity | Ω·m |
| \(L\) | Anode (or backfill column) length | m |
| \(d\) | Anode (or backfill column) diameter | m |
| \(\Delta V\) | Driving voltage (anode to protected structure) | V |
| \(I_{req}\) | Total protection current required | A |
| \(R_a\) | Anode resistance to earth | Ω |
| \(I_a\) | Current output per anode | A |
| \(N\) | Anodes needed (rounded up) | - |
Method and standards
Anode resistance.
Where it is used
- Galvanic CP design for pipelines and tanks.
- Checking anode output from soil surveys.
Common mistakes
- Using the bare anode size when backfill controls.
- Ignoring mutual interference in groups.
Assumptions and limits
- Single vertical anode in uniform resistivity; top at the surface neglected.
References
- Dwight's resistance of a vertical rod
Questions and answers
Why are magnesium anodes used in soil?
Their higher driving voltage pushes useful current through high-resistivity soil.
Does the anode's life follow from this?
Divide the anode's usable charge (mass × capacity × utilisation) by its current; see the anode mass calculator.
What do the defaults represent?
An illustrative 1.5 m × 200 mm backfilled magnesium anode column in 20 Ω·m soil with 0.7 V drive and 0.6 A demand.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Peabody, Control of Pipeline Corrosion, 2nd ed. (NACE, 2001)