Machine Hour Rate (Cost of Running a Machine per Hour)

Cost per running hour of a machine from depreciation, interest, maintenance, power, operator wages and overheads, for costing and quoting.

Inputs

Examples: Illustrative 2.5 million machineCNC machining centreSmall lathe, one shift

Accepted: 0 to 1E+12
Accepted: 0 to 1E+12
Accepted: 1 to 50
Accepted: 0 to 50 %
Accepted: 0 to 50 %
Accepted: 0 to 10,000 kW
Accepted: 0 to 100 %
Accepted: 0 to 1,000
Accepted: 0 to 100,000
Accepted: 0 to 1E+12
Accepted: 1 to 8,760

Results

The machine hour rate spreads the yearly fixed costs (straight-line depreciation, interest on the average investment (P + S)/2, maintenance and overheads) over the running hours, and adds the costs that come with each hour (power at the average load, the operator). Fewer running hours raise the rate sharply, which is why idle machines are expensive.

Depreciation per hour20.370
Interest per hour16.250
Maintenance per hour13.333
Power per hour22.000
Overheads per hour22.222
Machine hour rate including the operator294.18

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Illustrative 2.5 million machine. The inputs, in the units selected above:

InputValue
Purchase price2,500,000 -
Salvage value250,000 -
Life (years)10.000 -
Interest rate on the average investment10.000 %
Maintenance per year as a share of price5.0000 %
Connected power15.000 kW
Average load factor60.000 %
Electricity price per kWh8.0000 -
Operator cost per hour250.00 -
Overheads per year (space, insurance, supervision)120,000 -
Running hours per year3,000.0 -

Applying the formula below gives:

ResultValue
Depreciation per hour75.000
Interest per hour45.833
Maintenance per hour41.667
Power per hour72.000
Overheads per hour40.000
Machine hour rate including the operator524.50

Open this example in the calculator and change any input.

Formula

\(MHR = \frac{(P - S)/n + i(P + S)/2 + mP + O}{H} + P_e f_l c_e + w\)

Variables

Symbol Meaning SI unit
\(P\) Purchase price -
\(S\) Salvage value -
\(n\) Life (years) -
\(i\) Interest rate on the average investment -
\(m\) Maintenance per year as a share of price -
\(P_e\) Connected power W
\(f_l\) Average load factor -
\(c_e\) Electricity price per kWh -
\(w\) Operator cost per hour -
\(O\) Overheads per year (space, insurance, supervision) -
\(H\) Running hours per year -
\(D/H\) Depreciation per hour -
\(I/H\) Interest per hour -
\(M/H\) Maintenance per hour -
\(E\) Power per hour -
\(O/H\) Overheads per hour -
\(MHR\) Machine hour rate including the operator -

Method and standards

Machine hour rate.

Where it is used

  • Workshop costing and quotations.
  • Make-or-buy decisions.

Common mistakes

  • Spreading fixed costs over available instead of running hours.
  • Using connected power without a load factor.

Assumptions and limits

  • Straight-line depreciation; average investment for interest.

References

  • Machine hour rate costing

Questions and answers

Why is interest on the average investment used?

The money tied up falls from P to S over the life, so on average it is (P + S)/2.

How do running hours affect the rate?

Fixed costs are spread over the hours, so halving the hours nearly doubles that part of the rate.

What do the defaults represent?

An illustrative 2.5 million machine with 250,000 salvage over 10 years, 15 kW at 60 % load, run 3,000 h a year.

Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Sources

Peters, Timmerhaus and West, Plant Design and Economics for Chemical Engineers, 5th ed. (McGraw-Hill, 2003)

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.