Worked example
Example: Illustrative item, 95 %. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Mean demand per day (units) | 40.000 - |
| Standard deviation of daily demand | 12.000 - |
| Lead time | 10.000 d |
| Cycle service level (chance of no stock-out per cycle) | 95.000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Safety factor | 1.6449 |
| Safety stock (units) | 62.418 |
| Expected demand over the lead time (units) | 400.00 |
| Reorder point (units) | 462.42 |
Open this example in the calculator and change any input.
Formula
\(SS = z\,\sigma_d\sqrt{L}, \quad ROP = \bar d L + SS\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(\bar d\) | Mean demand per day (units) | - |
| \(\sigma_d\) | Standard deviation of daily demand | - |
| \(L\) | Lead time | s |
| \(SL\) | Cycle service level (chance of no stock-out per cycle) | - |
| \(z\) | Safety factor | - |
| \(SS\) | Safety stock (units) | - |
| \(\bar d L\) | Expected demand over the lead time (units) | - |
| \(ROP\) | Reorder point (units) | - |
Method and standards
Reorder point.
Where it is used
- Stores and spare parts planning.
- Chemical and consumable stocks.
Common mistakes
- Using the standard deviation of monthly demand with a daily mean.
- Treating the service level as fill rate.
Assumptions and limits
- Normal, independent daily demand; fixed lead time.
References
- Normal-demand safety stock for a cycle service level
Questions and answers
What safety factor goes with 95 %?
z = 1.645; 99 % needs 2.326.
Why does safety stock grow only with the square root of lead time?
Daily variations partly cancel over a longer period.
What do the defaults represent?
An illustrative item used at 40 a day (standard deviation 12) with a 10-day lead time at a 95 % service level.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Silver, Pyke and Peterson, Inventory Management and Production Planning and Scheduling, 3rd ed. (Wiley, 1998)