Worked example
Example: Illustrative project at 35 % earned. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Budget at completion | 1,000,000 - |
| Planned value to date | 400,000 - |
| Earned value to date | 350,000 - |
| Actual cost to date | 380,000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Cost variance EV − AC | -30,000 |
| Schedule variance EV − PV | -50,000 |
| Cost performance index | 0.92105 |
| Schedule performance index | 0.87500 |
| Estimate at completion BAC/CPI | 1,085,714 |
| Estimate to complete | 705,714 |
| Variance at completion | -85,714 |
| CPI needed on the remaining work to meet BAC | 1.0484 |
Open this example in the calculator and change any input.
Formula
\(CPI = \frac{EV}{AC}, \quad SPI = \frac{EV}{PV}, \quad EAC = \frac{BAC}{CPI}, \quad TCPI = \frac{BAC - EV}{BAC - AC}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(BAC\) | Budget at completion | - |
| \(PV\) | Planned value to date | - |
| \(EV\) | Earned value to date | - |
| \(AC\) | Actual cost to date | - |
| \(CV\) | Cost variance EV − AC | - |
| \(SV\) | Schedule variance EV − PV | - |
| \(CPI\) | Cost performance index | - |
| \(SPI\) | Schedule performance index | - |
| \(EAC\) | Estimate at completion BAC/CPI | - |
| \(ETC\) | Estimate to complete | - |
| \(VAC\) | Variance at completion | - |
| \(TCPI\) | CPI needed on the remaining work to meet BAC | - |
Method and standards
Earned value.
Where it is used
- Project cost and schedule control.
- Project management examinations.
Common mistakes
- Reading SPI late in a project (it tends to 1 at the end).
- Using percent spent as progress.
Assumptions and limits
- Current CPI continues.
References
- Industrial engineering practice (work study, line balancing, quality and project management)
Questions and answers
What do CPI 0.92 and SPI 0.875 mean?
The project gets 0.92 of budgeted work per unit spent and is 12.5 % behind schedule; it heads for about 1.086 million against 1 million budget.
What is TCPI?
The cost efficiency the remaining work must achieve to finish on budget: 1.05 here.
What do the defaults represent?
An illustrative 1,000,000 budget with 400,000 planned, 350,000 earned and 380,000 spent to date.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.