Worked example
Example: 15 m³/s, 10 m bed, 1.8 m deep. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Flow depth | 1.8000 m |
| Critical velocity ratio | 1.0000 - |
| Discharge | 54,000 m³/h |
| Bed width | 10.000 m |
| Side slope H:V | 0.50000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Critical velocity | 0.80119 m/s |
| Actual mean velocity | 0.76453 m/s |
| Velocity ratio | 0.95423 |
Open this example in the calculator and change any input.
Formula
\(V_0 = 0.55mD^{0.64}, \quad V = \frac{Q}{(B + zD)D}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(D\) | Flow depth | m |
| \(m\) | Critical velocity ratio | - |
| \(Q\) | Discharge | m³/s |
| \(B\) | Bed width | m |
| \(z\) | Side slope H:V | - |
| \(V_0\) | Critical velocity | m/s |
| \(V\) | Actual mean velocity | m/s |
| \(V/V_0\) | Velocity ratio | - |
Method and standards
Kennedy's equation.
Where it is used
- Checking existing canals.
- Exam problems.
Common mistakes
- Using FPS constant 0.84 with SI units.
- Ignoring the side slope in area.
Assumptions and limits
- Alluvial canals.
- V/V₀ within ±5 % of 1 is treated as non-silting, non-scouring; outside that band silting or scouring is flagged (an engineering tolerance, not part of Kennedy's equation).
References
- Kennedy's equation V₀ = 0.55mD^0.64 (SI) (Garg, Irrigation Engineering and Hydraulic Structures (Khanna))
Questions and answers
What is the critical velocity ratio?
m adjusts Kennedy's equation for silt: about 1.0 for Upper Bari Doab silt, 1.1–1.2 for coarser, 0.8–0.9 for finer.
Is Kennedy still used?
Mostly in teaching and checks; Lacey's regime theory replaced it for design.
What do the defaults represent?
A 15 m³/s canal 10 m wide and 1.8 m deep with 1:2 (0.5) side slopes.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.