Worked example
Example: Illustrative five-activity path. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Activity 1 optimistic | 2.0000 d |
| Activity 1 most likely | 4.0000 d |
| Activity 1 pessimistic | 6.0000 d |
| Activity 2 optimistic | 3.0000 d |
| Activity 2 most likely | 5.0000 d |
| Activity 2 pessimistic | 9.0000 d |
| Activity 3 optimistic | 4.0000 d |
| Activity 3 most likely | 6.0000 d |
| Activity 3 pessimistic | 8.0000 d |
| Activity 4 optimistic (0 = none) | 1.0000 d |
| Activity 4 most likely | 2.0000 d |
| Activity 4 pessimistic | 3.0000 d |
| Activity 5 optimistic (0 = none) | 5.0000 d |
| Activity 5 most likely | 7.0000 d |
| Activity 5 pessimistic | 12.000 d |
| Target completion time | 26.000 d |
Applying the formula below gives:
| Result | Value |
|---|---|
| Expected path duration | 24.833 d |
| Standard deviation of the path | 1.8333 d |
| Standard normal value | 0.63636 |
| Probability of finishing by the target | 73.773 % |
Open this example in the calculator and change any input.
Formula
\(t_e = \frac{a + 4m + b}{6}, \quad \sigma^2 = \sum\left(\frac{b - a}{6}\right)^2, \quad P = \Phi\left(\frac{T_s - T_e}{\sigma}\right)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(a_1\) | Activity 1 optimistic | s |
| \(m_1\) | Activity 1 most likely | s |
| \(b_1\) | Activity 1 pessimistic | s |
| \(a_2\) | Activity 2 optimistic | s |
| \(m_2\) | Activity 2 most likely | s |
| \(b_2\) | Activity 2 pessimistic | s |
| \(a_3\) | Activity 3 optimistic | s |
| \(m_3\) | Activity 3 most likely | s |
| \(b_3\) | Activity 3 pessimistic | s |
| \(a_4\) | Activity 4 optimistic (0 = none) | s |
| \(m_4\) | Activity 4 most likely | s |
| \(b_4\) | Activity 4 pessimistic | s |
| \(a_5\) | Activity 5 optimistic (0 = none) | s |
| \(m_5\) | Activity 5 most likely | s |
| \(b_5\) | Activity 5 pessimistic | s |
| \(T_s\) | Target completion time | s |
| \(T_e\) | Expected path duration | s |
| \(\sigma\) | Standard deviation of the path | s |
| \(z\) | Standard normal value | - |
| \(P\) | Probability of finishing by the target | - |
Method and standards
PERT.
Where it is used
- Shutdown and project planning.
- Project management examinations.
Common mistakes
- Ignoring near-critical paths.
- Using ranges that are not truly optimistic and pessimistic.
Assumptions and limits
- Independent activities; normal path duration.
References
- Industrial engineering practice (work study, line balancing, quality and project management)
Questions and answers
What is the chance of finishing the default path in 26 days?
Expected 24.8 days with σ 1.83 days: about 74 %.
Why (a + 4m + b)/6?
It is the mean of the beta distribution PERT assumes for each activity.
What do the defaults represent?
An illustrative five-activity critical path with optimistic, most likely and pessimistic times in days, and a 26-day target.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.