Levelised Cost of Electrolytic Hydrogen (LCOH)

Levelised cost of hydrogen from electrolyser capital and operating cost, capacity factor, specific energy and electricity price, with a breakdown per kg.

Chemical and fertiliser

Inputs

Examples: Illustrative 100 MW, 1000/kW, 50 %, 0.03/kWhSolar-coupled 25 % CF, 0.02/kWhGrid baseload 90 %, 0.06/kWh

Accepted: 0.001 to 10,000 MW
Accepted: 50 to 100,000
Accepted: 0 to 20 %
Accepted: 0 to 30 %
Accepted: 1 to 60
Accepted: 1 to 100 %
Accepted: 9.7222 to 111.11 kWh/kg
Accepted: 0 to 1

Results

LCOH = (CRF·C + O&M)/m_H₂ + c_e·e, CRF = i(1 + i)ⁿ/[(1 + i)ⁿ − 1]. Stack replacement, water, compression and storage are not included; add them as extra O&M or capital. At 55 kWh/kg each 0.01 per kWh of electricity adds 0.55 per kg.

Capital recovery factor9.4393%
Hydrogen per year2,027.8t
Capital cost per kg2.7930
O&M cost per kg0.73973
Electricity cost per kg1.0800
Levelised cost of hydrogen per kg4.6127

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Illustrative 100 MW, 1000/kW, 50 %, 0.03/kWh. The inputs, in the units selected above:

InputValue
Electrolyser rating100.00 MW
Installed cost (currency per kW)1,000.0 -
Fixed O&M (fraction of capital cost per year)3.0000 %
Discount rate8.0000 %
Economic life (years)20.000 -
Capacity factor50.000 %
System specific energy55.000 kWh/kg
Electricity price (currency per kWh)0.030000 -

Applying the formula below gives:

ResultValue
Capital recovery factor10.185 %
Hydrogen per year7,963.6 t
Capital cost per kg1.2790
O&M cost per kg0.37671
Electricity cost per kg1.6500
Levelised cost of hydrogen per kg3.3057

Open this example in the calculator and change any input.

Formula

\(LCOH = \frac{CRF\cdot C + f_{O\&M}C}{m_{H_2}} + c_ee, \quad CRF = \frac{i(1 + i)^n}{(1 + i)^n - 1}\)

Variables

Symbol Meaning SI unit
\(P\) Electrolyser rating W
\(C_{cap}\) Installed cost (currency per kW) -
\(f_{O\&M}\) Fixed O&M (fraction of capital cost per year) -
\(i\) Discount rate -
\(n\) Economic life (years) -
\(CF\) Capacity factor -
\(e\) System specific energy J/kg
\(c_e\) Electricity price (currency per kWh) -
\(CRF\) Capital recovery factor -
\(m_{H_2}\) Hydrogen per year kg
\(c_{cap}\) Capital cost per kg -
\(c_{O\&M}\) O&M cost per kg -
\(c_{el}\) Electricity cost per kg -
\(LCOH\) Levelised cost of hydrogen per kg -

Method and standards

Levelised cost of hydrogen.

Where it is used

  • Project screening and tariff design.
  • Comparing grey, blue and green hydrogen.

Common mistakes

  • Using stack specific energy instead of system energy.
  • Ignoring stack replacement over a 20-year life.

Assumptions and limits

  • Constant prices; no taxes, subsidies or inflation.

References

  • Levelised cost with a capital recovery factor

Questions and answers

What drives the cost of green hydrogen?

Electricity price and capacity factor: at 55 kWh/kg, power at 0.03 per kWh already costs 1.65 per kg, and a low capacity factor spreads the capital over fewer kilograms.

Why not run electrolysers only on surplus power?

Cheap surplus hours are few; below about 30–40 % capacity factor the capital cost per kg rises steeply.

What do the defaults represent?

An illustrative 100 MW electrolyser at 1,000 per kW, 3 % O&M, 8 % over 20 years, 50 % capacity factor, 55 kWh/kg and electricity at 0.03 per kWh.

Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Sources

Gilbert Masters, Renewable and Efficient Electric Power Systems (Wiley, 2004), ch. 5

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.