Worked example
Example: Illustrative 100 MW, 1000/kW, 50 %, 0.03/kWh. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Electrolyser rating | 100.00 MW |
| Installed cost (currency per kW) | 1,000.0 - |
| Fixed O&M (fraction of capital cost per year) | 3.0000 % |
| Discount rate | 8.0000 % |
| Economic life (years) | 20.000 - |
| Capacity factor | 50.000 % |
| System specific energy | 55.000 kWh/kg |
| Electricity price (currency per kWh) | 0.030000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Capital recovery factor | 10.185 % |
| Hydrogen per year | 7,963.6 t |
| Capital cost per kg | 1.2790 |
| O&M cost per kg | 0.37671 |
| Electricity cost per kg | 1.6500 |
| Levelised cost of hydrogen per kg | 3.3057 |
Open this example in the calculator and change any input.
Formula
\(LCOH = \frac{CRF\cdot C + f_{O\&M}C}{m_{H_2}} + c_ee, \quad CRF = \frac{i(1 + i)^n}{(1 + i)^n - 1}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(P\) | Electrolyser rating | W |
| \(C_{cap}\) | Installed cost (currency per kW) | - |
| \(f_{O\&M}\) | Fixed O&M (fraction of capital cost per year) | - |
| \(i\) | Discount rate | - |
| \(n\) | Economic life (years) | - |
| \(CF\) | Capacity factor | - |
| \(e\) | System specific energy | J/kg |
| \(c_e\) | Electricity price (currency per kWh) | - |
| \(CRF\) | Capital recovery factor | - |
| \(m_{H_2}\) | Hydrogen per year | kg |
| \(c_{cap}\) | Capital cost per kg | - |
| \(c_{O\&M}\) | O&M cost per kg | - |
| \(c_{el}\) | Electricity cost per kg | - |
| \(LCOH\) | Levelised cost of hydrogen per kg | - |
Method and standards
Levelised cost of hydrogen.
Where it is used
- Project screening and tariff design.
- Comparing grey, blue and green hydrogen.
Common mistakes
- Using stack specific energy instead of system energy.
- Ignoring stack replacement over a 20-year life.
Assumptions and limits
- Constant prices; no taxes, subsidies or inflation.
References
- Levelised cost with a capital recovery factor
Questions and answers
What drives the cost of green hydrogen?
Electricity price and capacity factor: at 55 kWh/kg, power at 0.03 per kWh already costs 1.65 per kg, and a low capacity factor spreads the capital over fewer kilograms.
Why not run electrolysers only on surplus power?
Cheap surplus hours are few; below about 30–40 % capacity factor the capital cost per kg rises steeply.
What do the defaults represent?
An illustrative 100 MW electrolyser at 1,000 per kW, 3 % O&M, 8 % over 20 years, 50 % capacity factor, 55 kWh/kg and electricity at 0.03 per kWh.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Gilbert Masters, Renewable and Efficient Electric Power Systems (Wiley, 2004), ch. 5