Motor Starting Voltage Dip Calculator (DOL)

Voltage dip at the bus when a large motor starts direct on line, from the transformer rating and impedance, the source fault level and the motor's starting kVA.

Thermal power plantProcess steam and utilitiesPumpFan and blowerElectric motor

Inputs

Examples: 1600 kVA, 6 % Z, 250 MVA source; 250 kW motor, 6 x FLC1000 kVA, 5 %, 100 MVA; 160 kW, 7 x2500 kVA, 6.25 %, 500 MVA; 450 kW, 5.5 x

Results

Voltage dip at the bus6.9301%
Motor starting kVA1,794.3kVA
Short-circuit kVA at the bus24.096MVA

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: 1600 kVA, 6 % Z, 250 MVA source; 250 kW motor, 6 x FLC. The inputs, in the units selected above:

InputValue
Transformer rating1,600.0 kVA
Transformer impedance6.0000 %
Upstream fault level at the transformer primary250.00 MVA
Motor rated output250.00 kW
Motor efficiency95.000 %
Motor full-load power factor88.000 %
Starting current, multiple of full-load current6.0000 -

Applying the formula below gives:

ResultValue
Voltage dip at the bus6.9301 %
Motor starting kVA1,794.3 kVA
Short-circuit kVA at the bus24.096 MVA

Open this example in the calculator and change any input.

Formula

\(S_{sc} = \left(\frac{z_T}{S_T} + \frac{1}{S_{src}}\right)^{-1} \qquad S_{st} = k\,\frac{P_m}{\eta\cos\varphi} \qquad \Delta V = \frac{S_{st}}{S_{st} + S_{sc}}\)

Variables

Symbol Meaning SI unit
\(S_T\) transformer rating VA
\(z_T\) transformer impedance –
\(S_{src}\) source fault level VA
\(P_m\) motor rated output W
\(\eta\) motor efficiency –
\(\cos\varphi\) full-load power factor –
\(k\) starting current multiple –
\(\Delta V\) voltage dip –
\(S_{st}\) motor starting kVA VA
\(S_{sc}\) short-circuit kVA at the bus VA

Method and standards

Approximate kVA (impedance) method: the starting motor and the source impedance form a divider; angles are neglected, which slightly overstates the dip.

Where it is used

  • Checking whether large feed pump and fan motors can start DOL.
  • Choosing starter type.
  • Transformer sizing for large motors.

Common mistakes

  • Ignoring other load already on the bus.
  • Using full-load instead of locked-rotor kVA.
  • Forgetting cable impedance to the motor.

Assumptions and limits

  • Infinite-bus approximation beyond the source fault level; resistances and angles neglected.
  • The cable from the bus to the motor and any load already on the bus are not included: the dip at the motor terminals is larger than the bus dip shown.

References

  • kVA (impedance) method for motor starting

Questions and answers

How much does the voltage dip when a big motor starts?

A 250 kW motor drawing 6 times full-load current takes about 1790 kVA at start; on a 1600 kVA, 6 % transformer fed from a 250 MVA source (24 MVA at the bus) the voltage dips about 6.9 %.

How much dip is acceptable?

Typically 10–15 % at the motor and less at other loads; contactors and drives may drop out at deeper dips. Check your plant's criteria.

How do I reduce it?

Star-delta, soft starter or VFD; a larger or lower-impedance transformer; or starting the motor from a stiffer bus.

Method and article reviewed by FireCAD engineering on 11 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.