Worked example
Example: 5 → 6 m/s, same ash. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Reference gas velocity | 5.0000 m/s |
| New gas velocity | 6.0000 m/s |
| Ash concentration ratio new/reference | 1.0000 - |
| Abrasion coefficient ratio (1 carbon steel, 0.7 alloy steel) | 1.0000 - |
| Operating hours ratio | 1.0000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Relative maximum erosion | 1.8251 |
| Velocity giving the reference erosion with the new ash and material | 5.0000 m/s |
Open this example in the calculator and change any input.
Formula
\(E_{max} \propto M\tau\rho_aV_g^{3.3} \Rightarrow \frac{E_2}{E_1} = \frac{M_2}{M_1}\cdot\frac{\tau_2}{\tau_1}\cdot\frac{\rho_{a2}}{\rho_{a1}}\left(\frac{V_2}{V_1}\right)^{3.3}, \quad V^* = V_1\left(\frac{M_2}{M_1}\cdot\frac{\rho_{a2}}{\rho_{a1}}\right)^{-1/3.3}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(V_1\) | Reference gas velocity | m/s |
| \(V_2\) | New gas velocity | m/s |
| \(\rho_{a2}/\rho_{a1}\) | Ash concentration ratio new/reference | - |
| \(M_2/M_1\) | Abrasion coefficient ratio (1 carbon steel, 0.7 alloy steel) | - |
| \(\tau_2/\tau_1\) | Operating hours ratio | - |
| \(E_2/E_1\) | Relative maximum erosion | - |
| \(V^*\) | Velocity giving the reference erosion with the new ash and material | m/s |
Method and standards
Basu's Eq. (11.1) as a ratio between a new and a reference condition. V* is the velocity that gives the reference erosion rate with the new ash and tube material (operating hours taken equal).
Where it is used
- Erosion assessments after fuel or load changes.
Common mistakes
- Using it for absolute erosion rates (it is a proportionality).
Assumptions and limits
- Same particle properties and impact angle.
- The ash concentration ratio must be above zero (at least 0.01): with no ash there is no erosion and \(V^*\) is not defined.
References
- Basu
- Circulating Fluidized Bed Boilers: Design
- Operation and Maintenance (Springer, 2015)
- ch. 11
- Eq. (11.1) (Chinese Boiler Thermal Standard 1973, after Finnie)
Questions and answers
Why the power 3.3?
Erosion grows with impact kinetic energy and the number of impacts, both rising with velocity.
Why do CFB walls erode less than bubbling-bed tubes?
Solids slide down CFB walls at low velocity and grazing angle.
What does alloy steel give?
M ≈ 0.7: about 30 % less erosion than carbon steel.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.