Fluidised-Bed Tube Erosion: Effect of Velocity and Ash

Relative maximum erosion of boiler tubes when gas velocity, ash concentration, operating hours or tube material change, by Emax ∝ M τ ρ_a V³·³ (Basu Eq. 11.1).

Thermal power plantProcess steam and utilitiesSugar mill and cogenerationChemical and fertiliserPulp and paperBoilerEconomiser and air preheater

Inputs

Examples: 5 → 6 m/s, same ashAlloy tubes, 30 % more ash

Results

A 20 % rise in velocity raises erosion by about 80 %: velocity is the first thing to control.

V* holds the operating hours equal; it is the velocity giving the reference erosion rate with the new ash and material.

Relative maximum erosion1.8251
Velocity giving the reference erosion with the new ash and material5.0000m/s

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: 5 → 6 m/s, same ash. The inputs, in the units selected above:

InputValue
Reference gas velocity5.0000 m/s
New gas velocity6.0000 m/s
Ash concentration ratio new/reference1.0000 -
Abrasion coefficient ratio (1 carbon steel, 0.7 alloy steel)1.0000 -
Operating hours ratio1.0000 -

Applying the formula below gives:

ResultValue
Relative maximum erosion1.8251
Velocity giving the reference erosion with the new ash and material5.0000 m/s

Open this example in the calculator and change any input.

Formula

\(E_{max} \propto M\tau\rho_aV_g^{3.3} \Rightarrow \frac{E_2}{E_1} = \frac{M_2}{M_1}\cdot\frac{\tau_2}{\tau_1}\cdot\frac{\rho_{a2}}{\rho_{a1}}\left(\frac{V_2}{V_1}\right)^{3.3}, \quad V^* = V_1\left(\frac{M_2}{M_1}\cdot\frac{\rho_{a2}}{\rho_{a1}}\right)^{-1/3.3}\)

Variables

Symbol Meaning SI unit
\(V_1\) Reference gas velocity m/s
\(V_2\) New gas velocity m/s
\(\rho_{a2}/\rho_{a1}\) Ash concentration ratio new/reference -
\(M_2/M_1\) Abrasion coefficient ratio (1 carbon steel, 0.7 alloy steel) -
\(\tau_2/\tau_1\) Operating hours ratio -
\(E_2/E_1\) Relative maximum erosion -
\(V^*\) Velocity giving the reference erosion with the new ash and material m/s

Method and standards

Basu's Eq. (11.1) as a ratio between a new and a reference condition. V* is the velocity that gives the reference erosion rate with the new ash and tube material (operating hours taken equal).

Where it is used

  • Erosion assessments after fuel or load changes.

Common mistakes

  • Using it for absolute erosion rates (it is a proportionality).

Assumptions and limits

  • Same particle properties and impact angle.
  • The ash concentration ratio must be above zero (at least 0.01): with no ash there is no erosion and \(V^*\) is not defined.

References

  • Basu
  • Circulating Fluidized Bed Boilers: Design
  • Operation and Maintenance (Springer, 2015)
  • ch. 11
  • Eq. (11.1) (Chinese Boiler Thermal Standard 1973, after Finnie)

Questions and answers

Why the power 3.3?

Erosion grows with impact kinetic energy and the number of impacts, both rising with velocity.

Why do CFB walls erode less than bubbling-bed tubes?

Solids slide down CFB walls at low velocity and grazing angle.

What does alloy steel give?

M ≈ 0.7: about 30 % less erosion than carbon steel.

Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.