FireCADCalc

Earned Value: CPI, SPI, EAC and Variances

Cost and schedule variances, cost and schedule performance indices, estimate at completion, estimate to complete, variance at completion and TCPI of a project.

Inputs

Examples: Illustrative project at 35 % earnedAhead and under budgetLate overrun

Accepted: 1 to 1E+15
Accepted: 0 to 1E+15
Accepted: 0 to 1E+15
Accepted: 0 to 1E+15

Results

Earned value compares the budgeted cost of work done (EV) with what was planned (PV) and what it cost (AC). CPI below 1 means over budget, SPI below 1 behind schedule. If the cost performance so far continues, the project will cost BAC/CPI; TCPI shows the efficiency the remaining work needs to come in on budget, and values well above 1.1 are rarely achieved. Other EAC formulas (AC + BAC − EV, or using CPI × SPI) suit other assumptions.

Cost variance EV − AC-40,000
Schedule variance EV − PV-30,000
Cost performance index0.78947
Schedule performance index0.83333
Estimate at completion BAC/CPI253,333
Estimate to complete63,333
Variance at completion-53,333
CPI needed on the remaining work to meet BAC5.0000

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Illustrative project at 35 % earned. The inputs, in the units selected above:

InputValue
Budget at completion1,000,000 -
Planned value to date400,000 -
Earned value to date350,000 -
Actual cost to date380,000 -

Applying the formula below gives:

ResultValue
Cost variance EV − AC-30,000
Schedule variance EV − PV-50,000
Cost performance index0.92105
Schedule performance index0.87500
Estimate at completion BAC/CPI1,085,714
Estimate to complete705,714
Variance at completion-85,714
CPI needed on the remaining work to meet BAC1.0484

Open this example in the calculator and change any input.

Formula

\(CPI = \frac{EV}{AC}, \quad SPI = \frac{EV}{PV}, \quad EAC = \frac{BAC}{CPI}, \quad TCPI = \frac{BAC - EV}{BAC - AC}\)

Variables

Symbol Meaning SI unit
\(BAC\) Budget at completion -
\(PV\) Planned value to date -
\(EV\) Earned value to date -
\(AC\) Actual cost to date -
\(CV\) Cost variance EV − AC -
\(SV\) Schedule variance EV − PV -
\(CPI\) Cost performance index -
\(SPI\) Schedule performance index -
\(EAC\) Estimate at completion BAC/CPI -
\(ETC\) Estimate to complete -
\(VAC\) Variance at completion -
\(TCPI\) CPI needed on the remaining work to meet BAC -

Method and standards

Earned value.

Where it is used

  • Project cost and schedule control.
  • Project management examinations.

Common mistakes

  • Reading SPI late in a project (it tends to 1 at the end).
  • Using percent spent as progress.

Assumptions and limits

  • Current CPI continues.

References

  • Industrial engineering practice (work study, line balancing, quality and project management)

Questions and answers

What do CPI 0.92 and SPI 0.875 mean?

The project gets 0.92 of budgeted work per unit spent and is 12.5 % behind schedule; it heads for about 1.086 million against 1 million budget.

What is TCPI?

The cost efficiency the remaining work must achieve to finish on budget: 1.05 here.

What do the defaults represent?

An illustrative 1,000,000 budget with 400,000 planned, 350,000 earned and 380,000 spent to date.

Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.