Worked example
Example: 20 000 m3/h, 300 m3 bed. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Gas flow | 20,000 m³/h |
| Bed volume | 300.00 m³ |
| Bed depth | 1.2000 m |
| Inlet concentration | 200.00 mg/m³ |
| Outlet concentration | 20.000 mg/m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Empty-bed contact time | 54.000 s |
| Bed area | 250.00 m² |
| Surface loading | 80.000 m/h |
| Mass loading | 0.013333 kg/(m³·h) |
| Elimination capacity | 0.012000 kg/(m³·h) |
| Removal efficiency | 90.000 % |
Open this example in the calculator and change any input.
Formula
\(EBCT = \frac{V}{Q}, \quad L_m = \frac{QC_{in}}{V}, \quad EC = \frac{Q(C_{in} - C_{out})}{V}, \quad \eta = 1 - \frac{C_{out}}{C_{in}}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(Q\) | Gas flow | m³/s |
| \(V\) | Bed volume | m³ |
| \(H\) | Bed depth | m |
| \(C_{in}\) | Inlet concentration | kg/m³ |
| \(C_{out}\) | Outlet concentration | kg/m³ |
| \(EBCT\) | Empty-bed contact time | s |
| \(A\) | Bed area | m² |
| \(q_s\) | Surface loading | m/s |
| \(L_m\) | Mass loading | kg/(m³·s) |
| \(EC\) | Elimination capacity | kg/(m³·s) |
| \(\eta\) | Removal efficiency | - |
Method and standards
Biofilter definitions.
Where it is used
- Effluent plant and composting odour control.
- Low-concentration VOC vents.
Common mistakes
- Overloading beyond the medium's elimination capacity.
- Letting the bed dry out.
Assumptions and limits
- Steady loading.
- Loadings are shown in kg/(m³·h) (1 kg/(m³·h) = 1 000 g/(m³·h)); FPS in lb per 1 000 ft³ per day.
References
- Cooper and Alley
- Air Pollution Control: A Design Approach
- 4th ed. (Waveland, 2011)
- ch. 15 (biofiltration: EBCT, loading and elimination capacity)
Questions and answers
What is EBCT?
Bed volume divided by gas flow: the time the gas would take to pass the bed if it were empty.
What is elimination capacity?
Grams of pollutant removed per cubic metre of bed per hour; it levels off at high loading.
What do the defaults give?
20,000 m³/h through 300 m³ at 1.2 m: EBCT 54 s, 90 % removal of 200 mg/m³, elimination capacity about 12 g/(m³·h).
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.