Worked example
Example: 3000 m3/h at 500 mg/m3, 2 m3 bed. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Gas flow (same conditions as the concentration: both actual or both normal) | 3,000.0 m³/h |
| VOC concentration | 500.00 mg/m³ |
| Bed volume | 2.0000 m³ |
| Carbon bulk density | 450.00 kg/m³ |
| Working capacity (kg VOC per kg carbon) | 0.10000 kg/kg |
| Operating hours per day | 16.000 h |
Applying the formula below gives:
| Result | Value |
|---|---|
| Carbon in the bed | 900.00 kg |
| VOC load | 1.5000 kg/h |
| Bed life (operating hours) | 60.000 h |
| Bed life (calendar days) | 3.7500 |
| Contact time | 2.4000 s |
| Carbon used per year (365 days) | 87.600 t |
Open this example in the calculator and change any input.
Formula
\(t_b = \frac{m_cw_c}{QC}, \quad m_c = \rho_bV, \quad t_c = \frac{V}{Q}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(Q\) | Gas flow (same conditions as the concentration: both actual or both normal) | m³/s |
| \(C\) | VOC concentration | kg/m³ |
| \(V\) | Bed volume | m³ |
| \(\rho_b\) | Carbon bulk density | kg/m³ |
| \(w_c\) | Working capacity (kg VOC per kg carbon) | kg/kg |
| \(h_d\) | Operating hours per day | s |
| \(m_c\) | Carbon in the bed | kg |
| \(\dot m_{VOC}\) | VOC load | kg/s |
| \(t_b\) | Bed life (operating hours) | s |
| \(t_d\) | Bed life (calendar days) | - |
| \(t_c\) | Contact time | s |
| \(\dot m_{c,yr}\) | Carbon used per year (365 days) | kg |
Method and standards
Mass balance.
Where it is used
- Solvent and odour vents.
- Tank breathing and loading emissions.
Common mistakes
- Using equilibrium capacity.
- Ignoring humidity.
Assumptions and limits
- Constant load; working capacity from data.
- Flow and concentration on one basis: both at actual conditions or both at normal conditions (m³ at 0 °C, 1 atm).
References
- Cooper and Alley
- Air Pollution Control: A Design Approach
- 4th ed. (Waveland, 2011)
- ch. 12 (adsorption: working capacity and bed life)
Questions and answers
What is working capacity?
The VOC a bed actually holds before breakthrough, below the equilibrium capacity because part of the bed is in the mass-transfer zone.
Why does humidity matter?
Water competes for pores; above about 50 % relative humidity carbon capacity for VOCs falls sharply.
What do the defaults give?
3,000 m³/h at 500 mg/m³ on 900 kg of carbon at 10 %: 60 operating hours, about 4 days at 16 h/day.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.