Worked example
Example: Economiser 6 million, saves 2.4 million a year, 10 %, 15 years. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Investment (your currency) | 6,000,000 - |
| Annual saving (your currency per year) | 2,400,000 - |
| Annual operation and maintenance cost | 100,000 - |
| Discount rate | 10.000 % |
| Life of the project (years) | 15.000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Simple payback (years) | 2.6087 |
| Net present value (your currency) | 1.1494e+07 |
| Internal rate of return | 38.029 % |
| Net annual saving | 2,300,000 |
Open this example in the calculator and change any input.
Formula
\(PB = \frac{I}{S - M} \qquad NPV = -I + \sum_{k=1}^{n}\frac{S - M}{(1 + r)^k} \qquad 0 = -I + \sum_{k=1}^{n}\frac{S - M}{(1 + IRR)^k}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(I\) | investment, your currency | – |
| \(S\) | annual saving | – |
| \(M\) | annual operation and maintenance cost | – |
| \(r\) | discount rate | – |
| \(n\) | life of the project, years | – |
| \(PB\) | simple payback, years | – |
| \(NPV\) | net present value | – |
| \(IRR\) | internal rate of return | – |
| \(S - M\) | net annual saving | – |
| \(k\) | year number | – |
Method and standards
Discounted cash flow with equal net savings at the end of each year; the IRR is the discount rate at which the NPV is zero, found by bracketed root finding.
Where it is used
- Justifying economisers, air heaters, condensate recovery, insulation, VFDs and O₂ trim.
- Energy audit reports and capital requests.
- Comparing two options with different costs and savings.
Common mistakes
- Using the gross saving and forgetting the running cost of the new equipment.
- Mixing a nominal discount rate with savings in today's money.
- Counting a saving at full load when the boiler runs mostly at part load.
Assumptions and limits
- Equal savings every year; no salvage value, tax or inflation.
- Investment at the start of year one; whole years of life.
- Discount rate from 0 up to (not including) 100 %. An IRR outside −99 % to 1 000 % is not shown.
References
- Discounted cash flow (end-of-year convention)
- standard engineering economics
Questions and answers
How do I calculate payback, NPV and IRR?
Payback is the investment over the net annual saving. An economiser costing 6 million that saves 2.4 million a year with 0.1 million upkeep pays back in 2.6 years; over 15 years at 10 % its NPV is 11.5 million and its IRR 38 %.
Which should I use to decide?
Payback is easy and shows risk, but ignores what happens after it. NPV says how much value the project adds at your cost of money; IRR lets projects of different sizes be compared. Most companies set a payback limit and an IRR hurdle.
Are tax and inflation included?
No. Enter savings and costs in today's money and use a real discount rate, or add tax effects separately.
Method and article reviewed by FireCAD engineering on 10 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.