Worked example
Example: Illustrative crest +3 % to -2 %. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Station of the PVI | 1,500.0 m |
| Elevation of the PVI | 120.00 m |
| Incoming grade | 3.0000 % |
| Outgoing grade | -2.0000 % |
| Length before the PVI | 120.00 m |
| Length after the PVI | 200.00 m |
| Station to evaluate | 1,460.0 m |
Applying the formula below gives:
| Result | Value |
|---|---|
| BVC elevation | 116.40 m |
| EVC elevation | 116.00 m |
| Grade at the CVC | -0.12500 % |
| CVC elevation (under the PVI) | 118.12 m |
| Curve elevation at the station | 117.97 m |
| Station of the high or low point | 1,495.2 m |
Open this example in the calculator and change any input.
Formula
\(g_3 = \frac{g_1L_1 + g_2L_2}{L_1 + L_2}, \quad E_{CVC} = E_{BVC} + \frac{g_1 + g_3}2L_1, \quad y = E + gx + \frac{r}{2}x^2\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(Sta_{PVI}\) | Station of the PVI | m |
| \(E_{PVI}\) | Elevation of the PVI | m |
| \(g_1\) | Incoming grade | - |
| \(g_2\) | Outgoing grade | - |
| \(L_1\) | Length before the PVI | m |
| \(L_2\) | Length after the PVI | m |
| \(Sta_x\) | Station to evaluate | m |
| \(E_{BVC}\) | BVC elevation | m |
| \(E_{EVC}\) | EVC elevation | m |
| \(g_3\) | Grade at the CVC | - |
| \(E_{CVC}\) | CVC elevation (under the PVI) | m |
| \(E_x\) | Curve elevation at the station | m |
| \(Sta_{hl}\) | Station of the high or low point | m |
Method and standards
Unequal vertical curve.
Where it is used
- Highway and railway profiles.
- Matching levels at bridges and junctions.
Common mistakes
- Using equal-tangent formulas.
- Grades in % in the formulas.
Assumptions and limits
- Parabolic curves; stations in metres.
References
- Unequal-tangent vertical parabolic curve
Questions and answers
When is an unequal-tangent curve used?
When a symmetric curve would clash with a bridge, intersection or other fixed level on one side of the PVI.
Is the CVC grade the average of g₁ and g₂?
Only for equal tangents; otherwise it is the length-weighted average.
What do the defaults represent?
An illustrative curve: +3 % to −2 % at a PVI of station 1,500 m and 120.0 m, 120 m before and 200 m after, evaluated at station 1,460 m.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Ghilani and Wolf, Elementary Surveying: An Introduction to Geomatics, 13th ed. (Pearson, 2012)