Worked example
Example: Illustrative three measured sides. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Side 1 length | 120.00 m |
| Side 1 bearing | 30.000 ° |
| Side 2 length | 150.00 m |
| Side 2 bearing | 120.00 ° |
| Side 3 length | 100.00 m |
| Side 3 bearing | 200.00 ° |
| Side 4 length (0 if none) | 0 m |
| Side 4 bearing | 0 ° |
Applying the formula below gives:
| Result | Value |
|---|---|
| Sum of latitudes of measured sides | -65.046 m |
| Sum of departures of measured sides | 155.70 m |
| Length of the omitted side | 168.74 m |
| Bearing of the omitted side | 292.67 ° |
Open this example in the calculator and change any input.
Formula
\(l_x = \sqrt{(\Sigma L)^2 + (\Sigma D)^2}, \quad \theta_x = \text{atan2}(-\Sigma D, -\Sigma L)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(l_1\) | Side 1 length | m |
| \(\theta_1\) | Side 1 bearing | rad |
| \(l_2\) | Side 2 length | m |
| \(\theta_2\) | Side 2 bearing | rad |
| \(l_3\) | Side 3 length | m |
| \(\theta_3\) | Side 3 bearing | rad |
| \(l_4\) | Side 4 length (0 if none) | m |
| \(\theta_4\) | Side 4 bearing | rad |
| \(\Sigma L\) | Sum of latitudes of measured sides | m |
| \(\Sigma D\) | Sum of departures of measured sides | m |
| \(l_x\) | Length of the omitted side | m |
| \(\theta_x\) | Bearing of the omitted side | rad |
Method and standards
Omitted side.
Where it is used
- Traverses around obstacles.
- Computing an inaccessible closing line.
Common mistakes
- Using reduced bearings without quadrant signs.
- Treating the result as a closure check.
Assumptions and limits
- Error-free measured sides; closed traverse.
References
- Closure of latitudes and departures
Questions and answers
Why is this not a check?
All measurement errors are absorbed into the computed side, so the traverse appears to close perfectly.
Can two quantities on different sides be omitted?
Yes, but that needs a different solution (for example by the sine rule); this tool covers one complete side.
What do the defaults represent?
An illustrative four-sided traverse with three measured sides of 120, 150 and 100 m at 30°, 120° and 200°; side 4 is not used.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Punmia, Jain and Jain, Surveying, Vol. 1, 16th ed. (Laxmi, 2005)