Pipeline Grade Stakes: Invert, Cut and Grade Rod

Pipe invert at a stake from a starting invert and grade, the cut from stake top to invert, and the batter board height for a fixed grade rod.

Inputs

Examples: Illustrative sewer at 0.6 %Falling drain at -1 %Shallow pipe, stake below rod height

Accepted: 0 to 1,000,000 m
Accepted: -500 to 9,000 m
Accepted: -20 to 20 %
Accepted: 0 to 1,000,000 m
Accepted: -500 to 9,000 m
Accepted: 0.5 to 10 m

Results

Invert at any station = starting invert + grade × distance. Offset stakes are levelled and marked with the cut to the invert. A batter board set exactly one grade-rod length above the invert at each stake gives a string line parallel to the pipe, so the crew can check each pipe with the rod. Negative cut means fill. Allow for the pipe wall if staking to the crown or outside bottom.

Invert at the stake96.700m
Cut from stake top to invert3.1420m
Batter board elevation (invert + rod)99.700m
Batter board height above the stake top-142.00mm

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Illustrative sewer at 0.6 %. The inputs, in the units selected above:

InputValue
Station of the starting invert0 m
Starting invert elevation96.250 m
Pipe grade (+ rising with stationing)0.60000 %
Stake station75.000 m
Elevation of the stake top99.842 m
Grade rod length3.0000 m

Applying the formula below gives:

ResultValue
Invert at the stake96.700 m
Cut from stake top to invert3.1420 m
Batter board elevation (invert + rod)99.700 m
Batter board height above the stake top-142.00 mm

Open this example in the calculator and change any input.

Formula

\(I = I_0 + g(Sta - Sta_0), \quad C = E_{stake} - I, \quad E_{BB} = I + L_{rod}\)

Variables

Symbol Meaning SI unit
\(Sta_0\) Station of the starting invert m
\(I_0\) Starting invert elevation m
\(g\) Pipe grade (+ rising with stationing) -
\(Sta\) Stake station m
\(E_{stake}\) Elevation of the stake top m
\(L_{rod}\) Grade rod length m
\(I\) Invert at the stake m
\(C\) Cut from stake top to invert m
\(E_{BB}\) Batter board elevation (invert + rod) m
\(h_{BB}\) Batter board height above the stake top m

Method and standards

Grade stakes.

Where it is used

  • Sewer and drain construction.
  • Pipeline cut sheets.

Common mistakes

  • Grade sign reversed.
  • Staking to the crown instead of the invert.

Assumptions and limits

  • Uniform grade between stations.

References

  • Staking pipeline grades

Questions and answers

What is a cut sheet?

A table of stake stations with their cuts from stake top to invert, given to the excavation crew.

Why use batter boards?

A string at a fixed height above the invert lets the crew check grade continuously without an instrument.

What do the defaults represent?

An illustrative sewer rising at 0.6 % from invert 96.250 m at station 0, with a stake at station 75 m whose top is 99.842 m, and a 3 m grade rod.

Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Sources

Ghilani and Wolf, Elementary Surveying: An Introduction to Geomatics, 13th ed. (Pearson, 2012)

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.