Worked example
Example: Illustrative 101.35 to 106.80 m over 40 m. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Reduced level at point 1 | 101.35 m |
| Reduced level at point 2 | 106.80 m |
| Horizontal distance between the points | 40.000 m |
| Contour interval | 1.0000 m |
Applying the formula below gives:
| Result | Value |
|---|---|
| First contour value crossed | 102.00 m |
| Distance of the first contour from point 1 | 4.7706 m |
| Spacing between contours | 7.3394 m |
| Number of contours crossed | 5.0000 |
| Gradient (1 in …) | 7.3394 |
Open this example in the calculator and change any input.
Formula
\(x = D\frac{C - h_1}{h_2 - h_1}, \quad \Delta x = \frac{D\cdot CI}{|h_2 - h_1|}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(h_1\) | Reduced level at point 1 | m |
| \(h_2\) | Reduced level at point 2 | m |
| \(D\) | Horizontal distance between the points | m |
| \(CI\) | Contour interval | m |
| \(C_1\) | First contour value crossed | m |
| \(x_1\) | Distance of the first contour from point 1 | m |
| \(\Delta x\) | Spacing between contours | m |
| \(n\) | Number of contours crossed | - |
| \(g\) | Gradient (1 in …) | - |
Method and standards
Contours.
Where it is used
- Plotting contour maps from grid or spot levels.
- Earthwork and drainage planning.
Common mistakes
- Interpolating across a ridge or valley.
- Mixing plan and slope distances.
Assumptions and limits
- Uniform slope between the points.
References
- Linear interpolation of contours (indirect contouring)
Questions and answers
Why must the slope be uniform?
Linear interpolation assumes a straight ground line; across a ridge or hollow it puts contours in the wrong place.
How do I choose the contour interval?
From map scale, terrain and purpose: smaller for flat sites and engineering plans, larger for hilly country.
What do the defaults represent?
Illustrative spot levels of 101.35 and 106.80 m, 40 m apart on the plan, with a 1 m contour interval.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Punmia, Jain and Jain, Surveying, Vol. 1, 16th ed. (Laxmi, 2005)