Concrete Pour Planning: Truck Loads, Trucks and Layer Return Time

Truck loads and number of transit mixers to keep a pump supplied, pour duration, and the time to return to a layer, compared with the concrete's setting time.

Thermal power plantProcess steam and utilitiesSugar mill and cogeneration

Inputs

Examples: Illustrative 240 m3 raft at 30 m3/hMachine foundation 600 m3, two pumpsSmall slab 40 m3

Accepted: 0.5 to 20,000 m³
Accepted: 1 to 15 m³
Accepted: 1 to 360 m³/h
Accepted: 10 to 333.33 min
Accepted: 0.5 to 10,000 m²
Accepted: 100 to 1,000 mm
Accepted: 0.5 to 8.3333 h

Results

Trucks = ⌈q·t_c/c⌉ keeps the pump fed; layer return time = A_l·t_l/q must stay well below the setting time (a ratio below about 60–70 %) or retarder, more pumps or a smaller layer area is needed to avoid cold joints. Add a standby truck for long pours.

Truck loads7.0000
Pour duration2.6667h
Trucks needed3.0000
Layer return time60.000min
Return time to setting time40.000%

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Illustrative 240 m3 raft at 30 m3/h. The inputs, in the units selected above:

InputValue
Pour volume240.00 m³
Transit mixer capacity7.0000 m³
Placing rate30.000 m³/h
Truck round-trip cycle time75.000 min
Plan area of one layer300.00 m²
Layer thickness400.00 mm
Initial setting time at site conditions3.0000 h

Applying the formula below gives:

ResultValue
Truck loads35.000
Pour duration8.0000 h
Trucks needed6.0000
Layer return time240.00 min
Return time to setting time133.33 %

Open this example in the calculator and change any input.

Formula

\(n_l = \left\lceil\frac{V}{c}\right\rceil, \quad n_t = \left\lceil\frac{qt_c}{c}\right\rceil, \quad t_r = \frac{A_lt_l}{q}\)

Variables

Symbol Meaning SI unit
\(V\) Pour volume m³
\(c\) Transit mixer capacity m³
\(q\) Placing rate m³/s
\(t_c\) Truck round-trip cycle time s
\(A_l\) Plan area of one layer m²
\(t_l\) Layer thickness m
\(t_{set}\) Initial setting time at site conditions s
\(n_l\) Truck loads -
\(t_p\) Pour duration s
\(n_t\) Trucks needed -
\(t_r\) Layer return time s
\(t_r/t_{set}\) Return time to setting time -

Method and standards

Pour planning.

Where it is used

  • Raft, machine foundation and slab pours.
  • Ready-mix ordering.

Common mistakes

  • Planning without a standby truck.
  • Ignoring hot weather shortening setting time.

Assumptions and limits

  • Steady supply and placing rate.

References

  • Pour logistics and layer return time

Questions and answers

What is a cold joint?

A joint formed when fresh concrete is placed on a layer that has already begun to set, so the layers do not bond.

How can return time be shortened?

Smaller pour areas per layer, thinner layers, a second pump, or retarding admixtures to extend setting time.

What do the defaults represent?

An illustrative 240 m³ raft pumped at 30 m³/h from 7 m³ trucks on a 75-minute cycle, in 400 mm layers of 300 m² with 3-hour setting time.

Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Sources

Neville, Properties of Concrete, 5th ed. (Pearson, 2011)

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.