Worked example
Example: 10 m³, 190 x 90 x 90 mm bricks, 10 mm joints, 1:6. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Volume of brickwork | 10.000 m³ |
| Brick length | 190.00 mm |
| Brick width | 90.000 mm |
| Brick height | 90.000 mm |
| Mortar joint thickness | 10.000 mm |
| Sand parts per part of cement in the mortar | 6.0000 - |
| Dry volume factor of mortar | 1.3300 - |
| Allowance for broken bricks | 5.0000 % |
| Bulk density of cement | 1,440.0 kg/m³ |
| Mass of one cement bag | 50.000 kg |
Applying the formula below gives:
| Result | Value |
|---|---|
| Bricks per m³ of masonry (with joints) | 500.00 |
| Bricks to order, with the allowance | 5,250.0 |
| Wet mortar | 2.3050 m³ |
| Dry mortar materials | 3.0657 m³ |
| Cement | 630.65 kg |
| Cement bags | 12.613 |
| Sand | 2.6277 m³ |
Open this example in the calculator and change any input.
Formula
\(n = \frac{1}{(l + j)(w + j)(h + j)}, \quad N = n V (1 + k_w)\)
\(V_m = V - n V\, l w h, \quad V_{m,d} = f_d V_m\)
\(m_c = \frac{V_{m,d}}{1 + s} \rho_c, \quad V_s = V_{m,d} \frac{s}{1 + s}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(V\) | Volume of brickwork | m³ |
| \(l\) | Brick length | m |
| \(w\) | Brick width | m |
| \(h\) | Brick height | m |
| \(j\) | Mortar joint thickness | m |
| \(s\) | Sand parts per part of cement in the mortar | - |
| \(f_d\) | Dry volume factor of mortar | - |
| \(k_w\) | Allowance for broken bricks | - |
| \(\rho_c\) | Bulk density of cement | kg/m³ |
| \(m_b\) | Mass of one cement bag | kg |
| \(n\) | Bricks per m³ of masonry (with joints) | - |
| \(N\) | Bricks to order, with the allowance | - |
| \(V_m\) | Wet mortar | m³ |
| \(V_{m,d}\) | Dry mortar materials | m³ |
| \(m_c\) | Cement | kg |
| \(N_b\) | Cement bags | - |
| \(V_s\) | Sand | m³ |
Method and standards
Each brick with its share of joint occupies (l + j)(w + j)(h + j); the mortar is the wall volume not taken by bricks, converted to dry materials with a dry volume factor and shared in the mix ratio.
Where it is used
- Estimating walls, boundary walls and boiler house enclosures.
- Ordering bricks, cement and sand.
- Checking bills of quantities.
Common mistakes
- Using nominal brick size that already includes the joint.
- Forgetting frogs filled with mortar.
- Ignoring openings in the wall volume.
Assumptions and limits
- Solid bricks; uniform joints.
- The count puts a joint on all three faces of every brick (a modular cell), which suits walls one brick thick or more. In a half-brick wall the thickness has no joint, so it takes fewer bricks per m³ and less mortar; compute such walls from the face area instead.
- Mortar wastage not included.
References
- Masonry quantity estimation from brick and joint dimensions
Questions and answers
How many 190 × 90 × 90 mm bricks in 1 m³?
With 10 mm joints each brick takes 0.2 × 0.1 × 0.1 m, so 500 bricks; 10 m³ with 5 % breakage needs 5 250.
How much mortar?
The space left: 0.23 m³ wet per m³ here, 0.31 m³ dry with a 1.33 factor, giving 63 kg of cement per m³ in 1:6.
Why a dry factor for mortar?
Sand bulks and voids fill when mixed with water, so dry materials exceed the wet volume.