Worked example
Example: Cutting 40, 55, 75 m² over 30 m. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Area of the first cross section | 40.000 m² |
| Area of the section midway between them | 55.000 m² |
| Area of the second cross section | 75.000 m² |
| Distance between the first and second sections | 30.000 m |
| Swell (bulking) on excavation | 25.000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Volume, prismoidal formula | 1,675.0 m³ |
| Volume, average end area | 1,725.0 m³ |
| End-area minus prismoidal volume (positive: end area over-estimates) | 50.000 m³ |
| Loose volume to haul (prismoidal × swell) | 2,093.8 m³ |
Open this example in the calculator and change any input.
Formula
\(V_p = \frac{L}{6}(A_1 + 4 A_m + A_2)\)
\(V_e = \frac{L}{2}(A_1 + A_2), \quad V_l = V_p (1 + k_s)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(A_1\) | Area of the first cross section | m² |
| \(A_m\) | Area of the section midway between them | m² |
| \(A_2\) | Area of the second cross section | m² |
| \(L\) | Distance between the first and second sections | m |
| \(k_s\) | Swell (bulking) on excavation | - |
| \(V_p\) | Volume, prismoidal formula | m³ |
| \(V_e\) | Volume, average end area | m³ |
| \(V_e - V_p\) | End-area minus prismoidal volume (positive: end area over-estimates) | m³ |
| \(V_l\) | Loose volume to haul (prismoidal × swell) | m³ |
Method and standards
The prismoidal formula is Simpson's rule applied to the cross-section areas; the average end area method is the trapezoidal rule.
Where it is used
- Road, channel and embankment quantities.
- Foundation excavation and backfill.
- Checking contractor measurements.
Common mistakes
- Averaging the end areas for the middle section.
- Using the swollen volume for payment in the ground.
- Mixing cut and fill in one section.
Assumptions and limits
- Sections measured square to the centre line.
- Swell factor from soil type.
- The end-area method usually over-estimates; when the middle area exceeds the mean of the end areas it under-estimates and V_e − V_p is negative.
References
- Prismoidal formula (Simpson's rule) and average end area method (surveying practice)
Questions and answers
What is the cut between sections of 40 and 75 m² 30 m apart, 55 m² midway?
1 675 m³ by the prismoidal formula; the end-area method gives 1 725 m³, 3 % more.
Which method is right?
The prismoidal formula is exact for sections that vary as a quadratic; the end-area method is simpler and usually over-estimates.
What is swell?
Excavated soil bulks: 25 % swell makes 1 675 m³ in the ground 2 094 m³ to haul.