Trench Excavation with Side Slopes

Excavated volume of a trench with sloping sides from bottom width, depth, side slope and length, with the top width and the loose volume to haul.

Inputs

Examples: Pipe trench 1:2 sidesVertical sidesDeep cut in rock

Your soil's figure; roughly 10–30 % for soils, 40–60 % for rock.

Results

Safe side slopes depend on the soil and depth; follow your site's excavation safety rules and shoring needs.

Top width b + 2 z d2.1000m
Cross-section2.0250m²
Bank (in-place) volume202.50m³
Loose volume to haul253.13m³

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Pipe trench 1:2 sides. The inputs, in the units selected above:

InputValue
Bottom width0.60000 m
Depth1.5000 m
Side slope (horizontal per 1 vertical; 0 for vertical sides)0.50000 -
Length100.00 m
Swell (bulking) of the excavated soil25.000 %

Applying the formula below gives:

ResultValue
Top width b + 2 z d2.1000 m
Cross-section2.0250 m²
Bank (in-place) volume202.50 m³
Loose volume to haul253.13 m³

Open this example in the calculator and change any input.

Formula

\(A = (b + z d)\, d, \quad V = A L, \quad V_l = V(1 + s_w)\)

Variables

Symbol Meaning SI unit
\(b\) Bottom width m
\(d\) Depth m
\(z\) Side slope (horizontal per 1 vertical; 0 for vertical sides) -
\(L\) Length m
\(s_w\) Swell (bulking) of the excavated soil -
\(B\) Top width b + 2 z d m
\(A\) Cross-section m²
\(V\) Bank (in-place) volume m³
\(V_l\) Loose volume to haul m³

Method and standards

Trapezoidal section.

Where it is used

  • Pipe and cable trenches.
  • Haulage estimates.

Common mistakes

  • Forgetting swell.
  • Vertical sides assumed where battering is needed.

Assumptions and limits

  • The side slope z is horizontal run per 1 vertical (H:V). A slope written "1:2" may mean 1 H : 2 V (z = 0.5) or 1 V : 2 H (z = 2) depending on the convention; check before entering.

  • Uniform depth.

References

  • Trapezoidal prism volume

Questions and answers

100 m of 0.6 m wide, 1.5 m deep trench with sides at 0.5 horizontal to 1 vertical (z = 0.5)?

202.5 m³ in place, 253.1 m³ loose to haul.

Why does the volume grow when dug?

Loosened soil occupies more space: the swell.

Varying depth?

Use the prismoidal formula between sections.

Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.