Worked example
Example: Pipe trench 1:2 sides. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Bottom width | 0.60000 m |
| Depth | 1.5000 m |
| Side slope (horizontal per 1 vertical; 0 for vertical sides) | 0.50000 - |
| Length | 100.00 m |
| Swell (bulking) of the excavated soil | 25.000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Top width b + 2 z d | 2.1000 m |
| Cross-section | 2.0250 m² |
| Bank (in-place) volume | 202.50 m³ |
| Loose volume to haul | 253.13 m³ |
Open this example in the calculator and change any input.
Formula
\(A = (b + z d)\, d, \quad V = A L, \quad V_l = V(1 + s_w)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(b\) | Bottom width | m |
| \(d\) | Depth | m |
| \(z\) | Side slope (horizontal per 1 vertical; 0 for vertical sides) | - |
| \(L\) | Length | m |
| \(s_w\) | Swell (bulking) of the excavated soil | - |
| \(B\) | Top width b + 2 z d | m |
| \(A\) | Cross-section | m² |
| \(V\) | Bank (in-place) volume | m³ |
| \(V_l\) | Loose volume to haul | m³ |
Method and standards
Trapezoidal section.
Where it is used
- Pipe and cable trenches.
- Haulage estimates.
Common mistakes
- Forgetting swell.
- Vertical sides assumed where battering is needed.
Assumptions and limits
The side slope z is horizontal run per 1 vertical (H:V). A slope written "1:2" may mean 1 H : 2 V (z = 0.5) or 1 V : 2 H (z = 2) depending on the convention; check before entering.
Uniform depth.
References
- Trapezoidal prism volume
Questions and answers
100 m of 0.6 m wide, 1.5 m deep trench with sides at 0.5 horizontal to 1 vertical (z = 0.5)?
202.5 m³ in place, 253.1 m³ loose to haul.
Why does the volume grow when dug?
Loosened soil occupies more space: the swell.
Varying depth?
Use the prismoidal formula between sections.