Worked example
Example: 600 x 200 x 200 blocks, 1:6. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Wall area (less openings) | 100.00 m² |
| Block length | 600.00 mm |
| Block height | 200.00 mm |
| Block thickness (wall thickness) | 200.00 mm |
| Joint thickness | 10.000 mm |
| Allowance for broken blocks | 5.0000 % |
| Sand parts per part of cement | 6.0000 - |
| Dry volume factor of mortar | 1.3300 - |
| Bulk density of cement | 1,440.0 kg/m³ |
| Mass of one cement bag | 50.000 kg |
Applying the formula below gives:
| Result | Value |
|---|---|
| Blocks needed (with allowance) | 819.67 |
| Wall volume | 20.000 m³ |
| Wet mortar volume | 1.2646 m³ |
| Cement bags | 6.9201 |
| Sand volume | 1.4417 m³ |
Open this example in the calculator and change any input.
Formula
\(N = \frac{A}{(l + j)(h + j)}(1 + k_w), \quad V_m = A t - N_0\, l h t\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(A\) | Wall area (less openings) | m² |
| \(l\) | Block length | m |
| \(h\) | Block height | m |
| \(t\) | Block thickness (wall thickness) | m |
| \(j\) | Joint thickness | m |
| \(k_w\) | Allowance for broken blocks | - |
| \(s\) | Sand parts per part of cement | - |
| \(f_d\) | Dry volume factor of mortar | - |
| \(\rho_c\) | Bulk density of cement | kg/m³ |
| \(m_b\) | Mass of one cement bag | kg |
| \(N\) | Blocks needed (with allowance) | - |
| \(V_w\) | Wall volume | m³ |
| \(V_m\) | Wet mortar volume | m³ |
| \(N_b\) | Cement bags | - |
| \(V_s\) | Sand volume | m³ |
Method and standards
Geometry and dry volume method.
Where it is used
- Estimating and purchase.
- Checking contractor bills.
Common mistakes
- Not deducting openings.
- Mortar for thin-bed AAC.
Assumptions and limits
- Uniform wall, single leaf.
References
- Blocks per m² = 1/((l + j)(h + j)); mortar by dry volume (Common site practice (quantity estimating))
Questions and answers
600 × 200 × 200 blocks with 10 mm joints?
7.81 blocks per m²; 100 m² takes about 820 with 5 % allowance.
How much mortar?
About 1.26 m³ wet for 100 m².
Openings?
Deduct doors and windows from the area first.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.