Worked example
Example: 1 m³ of 1:1.5:3, w/c 0.5. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Volume of concrete (wet, in place) | 1.0000 m³ |
| Cement parts in the mix ratio | 1.0000 - |
| Sand parts | 1.5000 - |
| Coarse aggregate parts | 3.0000 - |
| Water–cement ratio by mass | 0.50000 - |
| Dry volume factor (voids and bulking) | 1.5400 - |
| Bulk density of cement | 1,440.0 kg/m³ |
| Mass of one cement bag | 50.000 kg |
Applying the formula below gives:
| Result | Value |
|---|---|
| Dry volume of materials | 1.5400 m³ |
| Cement | 403.20 kg |
| Cement bags | 8.0640 |
| Sand | 0.42000 m³ |
| Coarse aggregate | 0.84000 m³ |
| Water | 201.60 kg |
Open this example in the calculator and change any input.
Formula
\(V_d = f_d V\)
\(m_c = V_d \frac{c}{c + s + a} \rho_c, \quad N_b = m_c / m_b\)
\(V_s = V_d \frac{s}{c + s + a}, \quad V_a = V_d \frac{a}{c + s + a}, \quad m_w = (w/c)\, m_c\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(V\) | Volume of concrete (wet, in place) | m³ |
| \(c\) | Cement parts in the mix ratio | - |
| \(s\) | Sand parts | - |
| \(a\) | Coarse aggregate parts | - |
| \(w/c\) | Water–cement ratio by mass | - |
| \(f_d\) | Dry volume factor (voids and bulking) | - |
| \(\rho_c\) | Bulk density of cement | kg/m³ |
| \(m_b\) | Mass of one cement bag | kg |
| \(V_d\) | Dry volume of materials | m³ |
| \(m_c\) | Cement | kg |
| \(N_b\) | Cement bags | - |
| \(V_s\) | Sand | m³ |
| \(V_a\) | Coarse aggregate | m³ |
| \(m_w\) | Water | kg |
Method and standards
The nominal volume mix: the dry volume of loose materials is shared in the mix ratio; cement is converted to mass with its bulk density and water follows from the water–cement ratio.
Where it is used
- Site estimates and bills of quantities.
- Ordering cement and aggregate for foundations and floors.
- Checking contractors' material claims.
Common mistakes
- Forgetting the dry volume factor.
- Using cement particle density instead of bulk density.
- Adding wastage twice.
Assumptions and limits
- Nominal volume mix; no admixtures.
- Wastage not included. The bag count is fractional; a note gives the whole bags to order.
References
- Nominal (volume) mix method of site estimation
Questions and answers
How many cement bags for 1 m³ of 1:1.5:3 concrete?
With a dry volume factor of 1.54 and cement at 1 440 kg/m³: 403 kg, about 8.1 bags of 50 kg, with 0.42 m³ of sand and 0.84 m³ of aggregate.
Why multiply by 1.54?
The dry loose materials shrink when mixed with water and compacted: voids fill and sand bulking is lost, so more dry volume than the wet volume is needed.
Is a nominal mix good enough?
For estimating and minor work. Structural grades need a design mix with trial batches to the code you work to.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.