Worked example
Example: Typical frame. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Concrete in footings | 17.500 m³ |
| Steel ratio in footings | 60.000 kg/m³ |
| Concrete in columns | 5.8000 m³ |
| Steel ratio in columns | 180.00 kg/m³ |
| Concrete in beams | 7.3000 m³ |
| Steel ratio in beams | 130.00 kg/m³ |
| Concrete in slabs | 27.000 m³ |
| Steel ratio in slabs | 80.000 kg/m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Total steel | 5.2030 t |
| Total concrete | 57.600 m³ |
| Average steel per m³ | 90.330 kg/m³ |
Open this example in the calculator and change any input.
Formula
\(m = \sum V_i\, r_i, \quad \bar r = \frac{m}{\sum V_i}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(V_f\) | Concrete in footings | m³ |
| \(r_f\) | Steel ratio in footings | kg/m³ |
| \(V_c\) | Concrete in columns | m³ |
| \(r_c\) | Steel ratio in columns | kg/m³ |
| \(V_b\) | Concrete in beams | m³ |
| \(r_b\) | Steel ratio in beams | kg/m³ |
| \(V_s\) | Concrete in slabs | m³ |
| \(r_s\) | Steel ratio in slabs | kg/m³ |
| \(m\) | Total steel | kg |
| \(V\) | Total concrete | m³ |
| \(\bar r\) | Average steel per m³ | kg/m³ |
Method and standards
Weighted sum.
Where it is used
- Early cost estimates.
- Checking detailed quantities.
Common mistakes
- Using one ratio for all members.
- Ratios from different design codes.
Assumptions and limits
- Estimate only.
References
- Volume × steel ratio (Common site practice (quantity estimating))
Questions and answers
What do the defaults give?
About 5.2 t of steel for 57.6 m³ of concrete, about 90 kg/m³ on average.
Where do ratios come from?
Completed projects of the same type; detailing gives the real figure.
Why are columns highest?
They carry heavy longitudinal bars and close ties.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.