Worked example
Example: Illustrative 240 m3 raft at 30 m3/h. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Pour volume | 240.00 m³ |
| Transit mixer capacity | 7.0000 m³ |
| Placing rate | 30.000 m³/h |
| Truck round-trip cycle time | 75.000 min |
| Plan area of one layer | 300.00 m² |
| Layer thickness | 400.00 mm |
| Initial setting time at site conditions | 3.0000 h |
Applying the formula below gives:
| Result | Value |
|---|---|
| Truck loads | 35.000 |
| Pour duration | 8.0000 h |
| Trucks needed | 6.0000 |
| Layer return time | 240.00 min |
| Return time to setting time | 133.33 % |
Open this example in the calculator and change any input.
Formula
\(n_l = \left\lceil\frac{V}{c}\right\rceil, \quad n_t = \left\lceil\frac{qt_c}{c}\right\rceil, \quad t_r = \frac{A_lt_l}{q}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(V\) | Pour volume | m³ |
| \(c\) | Transit mixer capacity | m³ |
| \(q\) | Placing rate | m³/s |
| \(t_c\) | Truck round-trip cycle time | s |
| \(A_l\) | Plan area of one layer | m² |
| \(t_l\) | Layer thickness | m |
| \(t_{set}\) | Initial setting time at site conditions | s |
| \(n_l\) | Truck loads | - |
| \(t_p\) | Pour duration | s |
| \(n_t\) | Trucks needed | - |
| \(t_r\) | Layer return time | s |
| \(t_r/t_{set}\) | Return time to setting time | - |
Method and standards
Pour planning.
Where it is used
- Raft, machine foundation and slab pours.
- Ready-mix ordering.
Common mistakes
- Planning without a standby truck.
- Ignoring hot weather shortening setting time.
Assumptions and limits
- Steady supply and placing rate.
References
- Pour logistics and layer return time
Questions and answers
What is a cold joint?
A joint formed when fresh concrete is placed on a layer that has already begun to set, so the layers do not bond.
How can return time be shortened?
Smaller pour areas per layer, thinner layers, a second pump, or retarding admixtures to extend setting time.
What do the defaults represent?
An illustrative 240 m³ raft pumped at 30 m³/h from 7 m³ trucks on a 75-minute cycle, in 400 mm layers of 300 m² with 3-hour setting time.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Neville, Properties of Concrete, 5th ed. (Pearson, 2011)