Worked example
Example: Illustrative 20 m bored pile. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Working load carried at the tip | 300.00 kN |
| Working load carried by the shaft | 500.00 kN |
| Shaft friction distribution factor | 0.60000 - |
| Pile length | 20.000 m |
| Pile diameter | 500.00 mm |
| Pile modulus | 28.000 GPa |
| Soil modulus | 30.000 MPa |
| Soil Poisson's ratio | 0.30000 - |
Applying the formula below gives:
| Result | Value |
|---|---|
| Elastic shortening of the pile | 2.1827 mm |
| Settlement from tip load | 19.697 mm |
| Settlement from shaft load | 1.0171 mm |
| Total settlement | 22.897 mm |
Open this example in the calculator and change any input.
Formula
\(s_1 = \frac{(Q_{wp} + \xi Q_{ws})L}{A_pE_p}, \quad s_2 = \frac{q_{wp}D}{E_s}(1 - \nu_s^2)I_{wp}, \quad s_3 = \frac{Q_{ws}}{pL}\frac{D}{E_s}(1 - \nu_s^2)\left(2 + 0.35\sqrt{\frac LD}\right)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(Q_{wp}\) | Working load carried at the tip | N |
| \(Q_{ws}\) | Working load carried by the shaft | N |
| \(\xi\) | Shaft friction distribution factor | - |
| \(L\) | Pile length | m |
| \(D\) | Pile diameter | m |
| \(E_p\) | Pile modulus | Pa |
| \(E_s\) | Soil modulus | Pa |
| \(\nu_s\) | Soil Poisson's ratio | - |
| \(s_1\) | Elastic shortening of the pile | m |
| \(s_2\) | Settlement from tip load | m |
| \(s_3\) | Settlement from shaft load | m |
| \(s\) | Total settlement | m |
Method and standards
Pile settlement.
Where it is used
- Working-load settlement checks of piles.
- Comparing pile lengths and diameters.
Common mistakes
- Using ultimate instead of working loads.
- A soil modulus from the wrong depth.
Assumptions and limits
- Linear elastic soil and pile; circular pile; working load well below ultimate.
References
- Vesić's method for pile settlement
Questions and answers
Which part of the settlement dominates?
For long slender piles the shaft shortening; for short stubby piles in soft soil the tip settlement.
How do I split load between tip and shaft?
From a capacity analysis or load-test instrumentation; at working load most of it is usually carried by the shaft.
What do the defaults represent?
An illustrative 20 m, 500 mm concrete pile carrying 300 kN at the tip and 500 kN on the shaft in soil of 30 MPa modulus.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Das, Principles of Foundation Engineering, 7th ed. (Cengage, 2011), Bowles, Foundation Analysis and Design, 5th ed. (McGraw-Hill, 1996)