Fuel Stock for Days of Operation

Mass and volume of coal, biomass or oil to stock for a number of days at a firing rate and daily running hours, for yard and tank sizing.

Thermal power plantSugar mill and cogenerationPulp and paperBoilerTank and drum

Inputs

Examples: Coal 12 t/h, 24 h/day, 30 days, 0.8 t/m³Furnace oil 2 t/h, 20 h/day, 15 days, 950 kg/m³Bagasse 25 t/h, 24 h/day, 10 days, 0.12 t/m³

Enter your specification's or the regulator's stock requirement.

Results

Fuel to stock8,640.0t
Volume of the stock10,800m³
Fuel burnt per day288.00t

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: Coal 12 t/h, 24 h/day, 30 days, 0.8 t/m³. The inputs, in the units selected above:

InputValue
Average fuel firing rate12,000 kg/h
Running hours per day24.000 h
Days of stock30.000 -
Bulk density (liquid density for oil)800.00 kg/m³

Applying the formula below gives:

ResultValue
Fuel to stock8,640.0 t
Volume of the stock10,800 m³
Fuel burnt per day288.00 t

Open this example in the calculator and change any input.

Formula

\(m_d = \dot m_f\,t_d \qquad m = m_d\,d \qquad V = \frac{m}{\rho_b}\)

Variables

Symbol Meaning SI unit
\(\dot m_f\) average fuel firing rate kg/s
\(t_d\) running hours per day s
\(d\) days of stock –
\(\rho_b\) bulk density (liquid density for oil) kg/m³
\(m\) fuel to stock kg
\(V\) volume of the stock m³
\(m_d\) fuel burnt per day kg

Method and standards

Mass and volume balance at the average firing rate.

Where it is used

  • Planning coal yards, biomass sheds and oil tanks.
  • Setting minimum stock levels.
  • Checking storage after a load increase.

Common mistakes

  • Using design firing rate when actual load is lower.
  • Ignoring moisture changes in stored fuel.
  • Counting unusable stock below the reclaim level.

Assumptions and limits

  • Average firing rate over the stock period; use the MCR rate for a conservative stock.
  • Stockpile losses, moisture changes and unusable heel in tanks are not included.

References

  • Mass and volume balance

Questions and answers

How much coal should be stocked?

Firing rate × hours per day × days. A boiler burning 12 t/h around the clock needs 288 t a day, 8 640 t for 30 days, about 10 800 m³ at 0.8 t/m³.

How many days?

As your specification, fuel contract or regulator requires; the calculator does not suggest a number.

Does it size the stockpile area?

It gives the volume. The area follows from the pile shape and height the yard allows.

Method and article reviewed by FireCAD engineering on 10 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.