Worked example
Example: 5000 TCD, 10 t trucks. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Cane to deliver per day | 5,000.0 t/d |
| Payload per trip | 10.000 t |
| Turnaround time per trip (load, haul, unload, return) | 4.0000 h |
| Working hours per day | 12.000 h |
| Fleet availability | 85.000 % |
Applying the formula below gives:
| Result | Value |
|---|---|
| Trips per day | 500.00 |
| Whole trips per vehicle per day | 3.0000 |
| Vehicles needed (rounded up) | 197.00 |
| Vehicles needed (exact) | 196.08 |
Open this example in the calculator and change any input.
Formula
\(N_t = \frac{C_d \cdot 1\,\mathrm{d}}{W}, \quad n = \left\lfloor \frac{H_d}{T} \right\rfloor, \quad N_v = \left\lceil \frac{N_t}{n\,\alpha} \right\rceil\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(C_d\) | Cane to deliver per day | kg/s |
| \(W\) | Payload per trip | kg |
| \(T\) | Turnaround time per trip (load, haul, unload, return) | s |
| \(H_d\) | Working hours per day | s |
| \(\alpha\) | Fleet availability | - |
| \(N_t\) | Trips per day | - |
| \(n\) | Whole trips per vehicle per day | - |
| \(N_v\) | Vehicles needed (rounded up) | - |
| \(N_f\) | Vehicles needed (exact) | - |
Method and standards
Haulage arithmetic.
Where it is used
- Season transport planning.
- Checking contractors' fleet offers.
Common mistakes
- Using the vehicle's rated payload instead of the average delivered load.
- Ignoring queueing time at the mill.
Assumptions and limits
- Average turnaround over the day. Each vehicle makes only whole trips in its working day (n is rounded down).
- C_d is the daily tonnage (1 d = 86 400 s).
References
- Haulage arithmetic: trips = daily tonnage / payload; vehicles = trips / (trips per vehicle × availability)
Questions and answers
What goes into the turnaround?
Waiting and loading in the field, haul, queue and weighing at the mill, unloading, and the return trip.
Why availability?
Vehicles break down and drivers rest; 80–90 % is a common planning figure.
Does the yard stock change the fleet?
Only the delivery hours: a fleet working fewer hours per day needs more vehicles.
Method and article reviewed by FireCAD engineering on 13 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.