Worked example
Example: Hugot: 12 h transport, 3 h reserve. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Crushing rate | 250.00 t/h |
| Crushing hours per day | 24.000 h |
| Hours per day in which cane is delivered | 12.000 h |
| Reserve kept in the yard (hours of crushing) | 3.0000 h |
Applying the formula below gives:
| Result | Value |
|---|---|
| Cane to hold in the yard at the end of deliveries | 3,750.0 t |
| Stock in hours of crushing | 15.000 h |
| Delivery rate needed while cane arrives | 500.00 t/h |
Open this example in the calculator and change any input.
Formula
\(P = A\,(t_c - t_d) + A\,t_r \quad\text{(Hugot: } P = 12A + 3A = 15A)\)
\(\dot m_d = \frac{A\,t_c}{t_d}\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(A\) | Crushing rate | kg/s |
| \(t_c\) | Crushing hours per day | s |
| \(t_d\) | Hours per day in which cane is delivered | s |
| \(t_r\) | Reserve kept in the yard (hours of crushing) | s |
| \(P\) | Cane to hold in the yard at the end of deliveries | kg |
| \(P/A\) | Stock in hours of crushing | s |
| \(\dot m_d\) | Delivery rate needed while cane arrives | kg/s |
Method and standards
Hugot's cane-yard balance: the cane delivered during transport hours must carry the crush through the hours without deliveries plus a reserve.
Where it is used
- Planning cane yards and night stock for a new crush rate.
- Checking whether the transport hours suit the crush.
Common mistakes
- Counting the reserve twice when transport also runs at night.
- Forgetting that the delivery rate must exceed the crush rate when deliveries stop at night.
Assumptions and limits
- Steady crush; delivery evenly spread over the delivery hours, and all delivery hours fall within crushing hours. If the mill stops while cane still arrives, the stock needed differs.
- Hugot's case: 12 hours of daylight transport, 24 hours of crushing and 3 hours of reserve give P = 15 A.
References
- Hugot
- Handbook of Cane Sugar Engineering
- 3rd ed. (Elsevier, 1986)
- ch. 1
- eqns 1.1–1.3
- p. 1
Questions and answers
Why hold cane overnight?
Cane usually arrives by day but the mill crushes round the clock; the yard bridges the hours without deliveries.
How big a reserve?
Hugot takes three hours of crushing, enough to ride through a short break in transport.
Is a large stock good?
No. Cut cane loses sucrose and weight while it waits; keep the stock as small as the transport allows.