Worked example
Example: 1 L per pulse, 50 m³/h, 10 Hz input. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Volume per pulse from the meter | 1.0000 L |
| Maximum flow | 50.000 m³/h |
| Highest pulse rate the counter or PLC input accepts | 10.000 Hz |
Applying the formula below gives:
| Result | Value |
|---|---|
| K-factor (pulses per m³) | 1,000.0 |
| Pulse frequency at maximum flow | 13.889 Hz |
| Smallest pulse divider within the limit (whole number, no margin) | 2.0000 |
| Volume per pulse after the divider | 2.0000 L |
| Pulse frequency after the divider | 6.9444 Hz |
| Pulses per day at maximum flow (after the divider) | 600,000 |
Open this example in the calculator and change any input.
Formula
\(K = \frac{1}{V_p}, \quad f = \frac{Q}{V_p}, \quad n = \left\lceil \frac{f}{f_{lim}} \right\rceil\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(V_p\) | Volume per pulse from the meter | m³ |
| \(Q_{max}\) | Maximum flow | m³/s |
| \(f_{lim}\) | Highest pulse rate the counter or PLC input accepts | 1/s |
| \(K\) | K-factor (pulses per m³) | - |
| \(f_{max}\) | Pulse frequency at maximum flow | 1/s |
| \(n\) | Smallest pulse divider within the limit (whole number, no margin) | - |
| \(V_{p,out}\) | Volume per pulse after the divider | m³ |
| \(f_{out}\) | Pulse frequency after the divider | 1/s |
| \(N_d\) | Pulses per day at maximum flow (after the divider) | - |
Method and standards
Pulse rate equals flow divided by volume per pulse.
Where it is used
- Configuring meters and PLCs.
- Totaliser checks.
Common mistakes
- Units of K mixed (per L vs per m³).
- No margin below the input limit.
Assumptions and limits
- Constant K-factor.
- The divider is the smallest that keeps the pulse rate at or below the limit, with no margin: choose a larger one for margin. Pulse width and duty cycle are not computed; check them against the input's minimum on-time.
References
- Pulse output relations f = Q/V_p
Questions and answers
What pulse rate does a 1 L/pulse meter give at 50 m³/h?
13.9 Hz, above a 10 Hz PLC input: divide by 2 for 2 L per pulse at 6.9 Hz.
What is the K-factor?
Pulses per unit volume: 1000 per m³ here.
Why check pulse width?
Slow inputs miss short pulses even below their rate limit.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.