NPV, IRR and Discounted Payback of a Project

Net present value, internal rate of return and simple and discounted payback of an investment that returns an annual saving, with optional escalation.

Inputs

Examples: 1 000 000 investment, 300 000 a year rising 5 %, 10 years, 10 %Economiser 2 500 000, 900 000 flat, 15 years, 12 %VFD 400 000, 100 000 rising 3 %, 8 years, 9 %

Results

Net present value (your currency)3,629,778
Internal rate of return35.628%
Simple payback (years)2.7778
Discounted payback (years; 0 = not within the life)3.5916
Profitability index (PV of savings ÷ investment)2.4519

Download PDF CSV Link to this result Compare another case

Log in to save calculations to your dashboard.

Worked example

Example: 1 000 000 investment, 300 000 a year rising 5 %, 10 years, 10 %. The inputs, in the units selected above:

InputValue
Investment at the start (your currency)1,000,000 -
Saving or net cash flow in year 1 (your currency)300,000 -
Yearly escalation of the saving5.0000 %
Life (years)10.000 -
Discount rate10.000 %

Applying the formula below gives:

ResultValue
Net present value (your currency)1,231,944
Internal rate of return31.944 %
Simple payback (years)3.3333
Discounted payback (years; 0 = not within the life)3.9209
Profitability index (PV of savings ÷ investment)2.2319

Open this example in the calculator and change any input.

Formula

\(NPV = -C_0 + \sum_{t=1}^{n}\frac{S\,(1+g)^{t-1}}{(1+i)^t} \qquad NPV(IRR) = 0 \qquad n_s = \frac{C_0}{S} \qquad PI = \frac{NPV + C_0}{C_0}\)

Variables

Symbol Meaning SI unit
\(C_0\) investment currency
\(S\) year-1 saving currency
\(g\) escalation –
\(n\) life years
\(i\) discount rate –
\(NPV\) net present value currency
\(IRR\) internal rate of return –
\(n_s\) simple payback years
\(n_d\) discounted payback years
\(PI\) profitability index –
\(t\) year –

Method and standards

End-of-year discounted cash flows; IRR by bisection; discounted payback interpolated within the year it turns positive.

Where it is used

  • Energy saving projects.
  • Equipment replacement.
  • Comparing options with different lives (with care).

Common mistakes

  • Comparing IRRs of projects of different size.
  • Forgetting tax and depreciation.
  • Escalating savings faster than the discount rate.

Assumptions and limits

  • End-of-year cash flows; no tax, depreciation or residual value.

References

  • Discounted cash flow (engineering economics)

Questions and answers

Is 1 000 000 for 300 000 a year (rising 5 %) over 10 years worth it at 10 %?

Yes: NPV 1.23 million, IRR 31.9 %, simple payback 3.3 years, discounted payback 3.9 years.

What discount rate should I use?

Your company's cost of capital or hurdle rate.

Why may there be no IRR?

If the undiscounted savings never repay the investment.

Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.

Related calculators

Free engineering calculators: every page computes in SI and converts to your units. Results are for engineering estimation; verify critical designs against the referenced standards.

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.