Worked example
Example: Illustrative 500 m2 yard, 200 x 100 blocks. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Paved area | 500.00 m² |
| Paver length | 200.00 mm |
| Paver width | 100.00 mm |
| Joint width | 3.0000 mm |
| Wastage and cuts | 5.0000 % |
| Compacted bedding sand thickness | 30.000 mm |
| Loose-to-compacted sand factor | 1.2500 - |
| Edge perimeter needing kerbs | 90.000 m |
| Kerb stone length | 500.00 mm |
Applying the formula below gives:
| Result | Value |
|---|---|
| Paver blocks | 25,109 |
| Blocks per square metre | 47.826 1/m |
| Loose bedding sand | 18.750 m³ |
| Kerb stones | 180.00 |
Open this example in the calculator and change any input.
Formula
\(N = \left\lceil\frac{A(1 + f_w)}{(l + j)(b + j)}\right\rceil, \quad V_s = At_sf_c\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(A\) | Paved area | m² |
| \(l\) | Paver length | m |
| \(b\) | Paver width | m |
| \(j\) | Joint width | m |
| \(f_w\) | Wastage and cuts | - |
| \(t_s\) | Compacted bedding sand thickness | m |
| \(f_c\) | Loose-to-compacted sand factor | - |
| \(L_e\) | Edge perimeter needing kerbs | m |
| \(l_k\) | Kerb stone length | m |
| \(N\) | Paver blocks | - |
| \(n/m^2\) | Blocks per square metre | 1/m |
| \(V_s\) | Loose bedding sand | m³ |
| \(n_k\) | Kerb stones | - |
Method and standards
Paving quantities.
Where it is used
- Plant roads, yards and footpaths.
- Parking areas.
Common mistakes
- Ignoring joint width.
- Ordering compacted rather than loose sand volume.
Assumptions and limits
- Rectangular blocks laid in a regular pattern.
References
- Modular paving layout
Questions and answers
How many 200 × 100 mm pavers per square metre?
About 49 with 3 mm joints, 50 with none.
Why must pavements have edge restraint?
Without kerbs or edging, blocks creep sideways under traffic and joints open.
What do the defaults represent?
An illustrative 500 m² yard in 200 × 100 mm blocks with 3 mm joints, 30 mm compacted bedding sand and 90 m of 500 mm kerbs.
Method and article reviewed by FireCAD engineering on 17 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.
Sources
Dutta, Estimating and Costing in Civil Engineering, 28th ed. (UBS, 2020)