Worked example
Example: 500 m3 compacted. The inputs, in the units selected above:
| Input | Value |
|---|---|
| Compacted volume required | 500.00 m³ |
| Shrinkage from bank to compacted | 10.000 % |
| Swell from bank to loose | 25.000 % |
| Truck capacity (loose) | 10.000 m³ |
Applying the formula below gives:
| Result | Value |
|---|---|
| Bank volume needed | 555.56 m³ |
| Loose volume to bring | 694.44 m³ |
| Truck loads (rounded up) | 70.000 |
Open this example in the calculator and change any input.
Formula
\(V_b = \frac{V_c}{1 - s_h}, \quad V_l = V_b(1 + s_w)\)
Variables
| Symbol | Meaning | SI unit |
|---|---|---|
| \(V_c\) | Compacted volume required | m³ |
| \(s_h\) | Shrinkage from bank to compacted | - |
| \(s_w\) | Swell from bank to loose | - |
| \(V_t\) | Truck capacity (loose) | m³ |
| \(V_b\) | Bank volume needed | m³ |
| \(V_l\) | Loose volume to bring | m³ |
| \(N\) | Truck loads (rounded up) | - |
Method and standards
Volume factors.
Where it is used
- Fill and backfill orders.
- Earthwork planning.
Common mistakes
- Confusing swell and shrinkage.
- Truck capacity in compacted volume.
Assumptions and limits
- Uniform material.
References
- Bank
- loose and compacted volume relations (earthmoving practice)
Questions and answers
500 m³ compacted with 10 % shrinkage and 25 % swell?
556 m³ of bank material, 694 m³ loose: 70 loads of 10 m³.
What is shrinkage?
Compacted fill is denser than the soil in its natural bank.
Where do factors come from?
Soil tests or earthmoving handbooks for the material.
Method and article reviewed by FireCAD engineering on 12 November 2026. Every result is checked against an independent calculation on each release: how we verify our calculators.